Construction Management
Capital-intensive projects where entitlement, financing, construction, and tenancy require multi-party coordination.
Inside this journey
-
Project Discovery
Align on the owner’s objectives, budget envelope, critical schedule drivers, key stakeholders, and primary project risks.
Discovery Questions
Tell Me About Your Project — Start Simple
- What is the project name and primary site address?
- Briefly describe the project in one sentence (purpose, size, and who will occupy it).
- Which of these best describes the building type?
- Which phase are you in right now?
- Who is the internal owner sponsor and who holds final budget approval?
- Which range best matches the current construction budget or target GMP?
- If you’d prefer to specify an exact budget or note important qualifiers (phasing, exclusions), please enter that here.
What Would Actually Break If the Schedule Slipped?
- If your target occupancy date moved back three months, what would be the immediate operational or financial consequences?
- Which of these are hard dates we must protect? (Select all that apply.)
- What are the top 2–3 activities that most commonly drive your critical path?
- How much schedule risk are you willing to accept before you expect the CM to escalate and propose mitigation (in days)?
- Have you experienced a schedule delay on a recent project that cascaded into other commitments? Tell us what happened and what you learned.
- Who on your team should be notified immediately if a critical path activity is at risk?
Where Is the Money Most Vulnerable?
- If the project exceeded budget by 5–10%, where would you expect those overruns to originate?
- Which of these cost categories concern you most? (Select up to three.)
- What contingency level have you assumed or established (% of construction cost)?
- How flexible is the budget envelope—can scope be reduced, or do you need absolute cost certainty before proceeding?
- What procurement approach are you leaning toward for trades? (This affects cost exposure.)
- Are there specific value-engineering targets or cost-saving areas you've already identified?
Who's Actually Making the Call When It Matters?
- When tough tradeoffs come up (budget vs. schedule vs. quality), who has final decision rights?
- Which stakeholders should be included in weekly decision updates? (Select all that apply.)
- Are any approvals subject to boards, public agencies, or external funding timetables that could limit rapid decision-making? Please explain.
- Describe a past instance where stakeholder misalignment caused delay or added cost—what was the root cause?
- How do you prefer major decisions to be documented and escalated? (Select all that apply.)
- Who on your team will be the day‑to‑day point of contact for the CM on site issues?
What’s Your Worst 'I Wish I'd Known' Construction Story?
- Think of a past project that left you frustrated—what single issue stands out and why did it hurt the most?
- Which of the following problems have you actually experienced? (Select all that apply.)
- How did vendor or contractor performance contribute to that outcome, and how did you try to manage it?
- What red flags would you want us to identify early when evaluating potential trade partners for this project?
- Would you like references and case studies from similar projects included in our proposal package?
If the Project Closed with Zero Surprises, What Would You Notice?
- Imagine handover day with no unresolved punchlist items—what are the first three success signals you'd point to?
- Which metrics would make you say the CM delivered exceptional value? (Select up to three.)
- How frequently do you want structured reporting during construction (high level vs. detailed)?
- What acceptance criteria or measurable benchmarks must be met before you consider work complete?
- What level of involvement do you expect from the CM during commissioning and turnover?
Are You Ready to Move — And What Would Make You Say Yes Today?
- What is the single most important condition that would make you comfortable awarding a construction management engagement now?
- What procurement timeline do you have in mind for issuing an RFP / engaging a CM and for awarding a contract?
- Which fee model do you prefer to discuss first?
- What documentation or approvals do you require before a CM can begin preconstruction work or mobilize? (Select all that apply.)
- Is there anything else—political, community, or organizational—that could make this engagement more complex than it appears on paper?
- What would be a reasonable next step from your perspective (e.g., introductory call, site visit, proposal request)?
-
Solution Experience
Apply the customer’s project scenarios to show how owner-rep construction management will prevent cost overruns, mitigate schedule slips, and manage trade contractor accountability.
Experience Meetings
- Current State & Risk Validation
- Scenario Workshop — Cost Overrun Prevention
- Scenario Workshop — Schedule Recovery & Trade Coordination
- Accountability, Change Governance & Acceptance Criteria
- Integrated Solution Confirmation — Diagnosis, Proof, Validation
- Owner to confirm approval thresholds and delegated signatories for change orders.
- Introductions & Meeting Frame
- Produce an agreed schedule recovery path with named owners for each critical milestone.
- Confirm which sequencing and procurement levers the owner authorizes to reduce delay risk.
- Identify required changes to mobilization and staffing to achieve the recovery plan.
- Owner to share the most recent master schedule in editable format and highlight lock/don't-change dates.
- Seller to prepare a mobilization & sequencing plan showing staffing ramps, procurement windows, and float recapture points.
- Both parties to agree on a short list of named subcontractors whose procurement timing is critical.
- Change-Order Governance Flow
- Agree on a practical change-order governance model with thresholds and SLAs.
- Approve an accountability matrix with named responsible parties for key contractor deliverables.
- Finalize measurable acceptance criteria for milestone handovers to prevent latent defects and rework.
- Seller to deliver a one-page change governance flowchart and a sample change-order template.
- A prioritized list of risks and named owner contacts for follow-up.
- Seller to draft acceptance checklists for the next major milestone and share for comment.
- Restate Current State, Consequence, Future State
- Obtain explicit owner validation that the proposed solution delivers the defined future state.
- Agree the set of deliverables, decisions, and data required to draft the Service Scope and commercial proposal.
- Capture any remaining objections and convert them into a short remediation plan with owners and timelines.
- Seller to produce a one-page 'how we prevent X' summary for the agreed scenario showing numeric outcomes.
- Both parties to confirm readiness checklist items (documents, approvals, decision-makers) required to proceed to Service Scope.
- Owner to schedule the internal sign-off meeting for procurement and budget authority within agreed timeline.
- Endorsed single-sentence current state that all participants can repeat.
- Quantified top 3 consequences (cost, schedule, operational) tied to project data or clearly stated assumptions.
- Owner to provide baseline budget, baseline schedule, and top 5 change-history items within 48 hours.
- Seller to produce a one-page risk register draft mapping risks to quantified consequences.
- All attendees to confirm stakeholder contact list and decision rights for the project.
- Scenario Recap & Baseline Assumptions
- Demonstrate a clear reduction in projected overrun for the scenario, with numeric delta and key assumptions.
- Achieve owner validation that proposed interventions map to the actual causes of cost escalation.
- Agree which interventions the owner wants included in the Service Scope and which require further approval.
- Seller to deliver the scenario cost model workbook with line-item assumptions and sensitivity analysis.
- Owner to confirm which VE options and contingency policy are acceptable for inclusion.
- Seller to draft procurement sourcing options and timelines tied to the cost model outcomes.
- Schedule Scenario & Critical Path Statement
- End-to-End Walkthrough of Proposed CM Solution
- Field Accountability Matrix
- Critical Dependencies & Bottlenecks
- Root Causes & Cost Drivers
- One-Sentence Current State
- Top 3 Project Risks & Who's Affected
- Targeted CM Interventions
- CM Controls & Recovery Tactics
- Tie Steps Back to Problems
- Measurable Acceptance Criteria
- Proof: Modeled Cost Impact
- Proof: Schedule Simulation & Checkpoints
- Stakeholder Validation & 'Is This Right?'
- Mock Change Scenario Walkthrough
- Consequence Quantification
- Next Steps & Governance Sign-Off
- Next Steps & Move-to-Service-Scope Checklist
- Validation & Assignment
- Validation & Consensus
- Validation & Clarifications
-
Service Scope
Define preconstruction and construction deliverables, on-site roles (PM/superintendent), reporting cadence, change-order governance, and measurable acceptance criteria.
Scope Configuration
- Daily On-Site Owner's Representative Presence
- Field Supervision and Superintendent Deployment
- Review and Process Pay Applications
- Negotiate and Execute Change Orders
- Administer Trade Contractor Bidding and Awards
- Manage RFIs and Construction Documentation
- Enforce Site Safety and Regulatory Compliance
- Implement Quality Control and Punchlist Resolution
- Review and Approve Submittals and Shop Drawings
- Oversee Mock-Ups and Sample Approvals
- Perform Commissioning Oversight and Systems Startup Support
- Assemble Closeout Documents and Handover Package
- Manage Warranty Claims and Post-Occupancy Deficiency Work
Scope Questions
Daily On-Site Owner's Representative Presence
- Do you require a full-time owner's representative on site?
- What core responsibilities should the on-site representative prioritize?
- Which hours or shifts must the representative cover (e.g., 7am-4pm)?
- Will the representative act as the primary client contact for daily decisions?
- Are weekend or night shift coverage requirements anticipated?
- Do you require daily onsite reporting (photo log, progress narrative)?
Field Supervision and Superintendent Deployment
- How many superintendents do you anticipate needing based on project phases or sites?
- Should superintendents be dedicated to this project or shared across projects?
- What on-site duties are mandatory for superintendent coverage (safety briefings, subcontractor coordination, inspections)?
- Do you require superintendent attendance at client or owner meetings?
- What level of superintendent experience/certification is required (years, specialties)?
- Are there union or site-specific labor rules that affect superintendent deployment?
Review and Process Pay Applications
- Do you want on-site verification (percent complete/quality) for each pay application?
- What frequency of pay application processing do you expect?
- What supporting documentation must be validated with each application (lien waivers, schedules, submittals)?
- Do you require cost-to-complete analysis or earned value reporting with applications?
- Who has final sign-off authority for payment approval?
- Are there preferred payment platforms or accounting integrations we must use?
Negotiate and Execute Change Orders
- What change order approval thresholds should trigger different workflows?
- Who are designated approvers for time-and-cost impacts (owner, PM, finance)?
- Do you want negotiated GMP adjustments, allowances, or provisional sums to be itemized?
- Should we establish pre-approved contingency use rules and delegated authority?
- What documentation is required to authorize a change (cost backup, schedule impact, scope description)?
- Are there insurance, bonding, or owner approval processes that affect execution timing?
Administer Trade Contractor Bidding and Awards
- Which procurement approach do you prefer for trades?
- Do you require prequalification criteria for bidders (financials, references, safety record)?
- What is the desired bid package granularity (divisional trades, bundled packages)?
- Do you want trade scope reviews and bid reconciliation performed by our estimating team?
- What award criteria should be prioritized (price, schedule, past performance, local preference)?
- Are there owner-mandated subcontractor diversity, local hire, or compliance requirements?
Manage RFIs and Construction Documentation
- What RFI turnaround times are required for critical-path items?
- Do you require an online document management system (DMS) for RFIs/submittals?
- What naming/version control conventions must be followed for drawings and documents?
- Should we implement an RFI prioritization process (critical, high, routine)?
- How frequently do you want consolidated document/status packages (weekly document log, open RFI list)?
- Are there third-party reviewers (engineers, vendors) who must be looped into documentation workflows?
Enforce Site Safety and Regulatory Compliance
- Do you require our team to act as the primary safety coordinator or to supplement trade supervision?
- What safety standards/regulations must be enforced (OSHA, local codes, project-specific)?
- Are site-specific training or certification requirements needed for workers (e.g., site orientation, drug testing)?
- Do you require daily/weekly safety reports and incident logs?
- Should safety compliance be tied to subcontractor payment or punchlist holdbacks?
- Are there environmental or permitting constraints we need to manage (noise, hours, protected species)?
Implement Quality Control and Punchlist Resolution
- What level of QC inspection frequency do you require (daily, weekly, milestone)?
- Do you want checklists and acceptance criteria documented for each trade or assembly?
- How should punchlist prioritization be handled (safety/critical first, then cosmetic)?
- Do you require progress tracking of punchlist items in a shared system with owner visibility?
- What acceptable resolution timelines do you expect for high, medium, and low priority punch items?
- Should final acceptance include independent third-party inspections or owner's own QA team?
Review and Approve Submittals and Shop Drawings
- What submittal turnaround times do you require for critical vs. non-critical items?
- Do you require staged submittal review gates (preliminary shop drawing review, final approval)?
- Should submittal review include coordination with design consultants and MEP leads?
- Are electronic submittal templates or markup standards required?
- How will unacceptable submittals be handled (revise/resubmit, holdback)?
- Do you require a submittal log with status visibility for owner and trades?
Oversee Mock-Ups and Sample Approvals
- Which trades or assemblies require mock-ups (facades, millwork, MEP rooms)?
- Do you prefer in-field mock-ups, off-site mock-ups, or vendor samples?
- What acceptance criteria must mock-ups meet before mass installation?
- Who will sign off mock-ups (owner rep, design team, consultant)?
- Are mock-up schedules and costs expected to be included in contractor scope or owner-directed?
- Do you require photographic and dimensional record of approved mock-ups for field reference?
-
Mutual Commit
Resolve fee structure, contract terms, milestones, decision rights, and readiness conditions for mobilization and procurement.
Agreement Modules
- Statement of Work (SOW)
- Master Services / Project Agreement (MSA)
- Fee Structure & Payment Schedule
- Milestones & Mobilization Readiness Conditions
- Decision Rights & Governance Matrix
- Change Order & Contingency Protocol
- Trade Procurement Authorization
- Staffing & Named Team Commitments
- Schedule Baseline & Key Critical Dates
- Insurance, Bonds & Risk Allocation
- Acceptance Criteria & Closeout Deliverables
- Reporting, Communication & Document Access
- Termination, Suspension & Remedies
-
Mobilization & Execution Plan
Plan mobilization, staffing assignments, trade procurement sequencing, key schedule milestones, and quality checkpoints with named owners.
-
Success & Closeout
Validate outcomes against success signals, complete punchlist and turnover, capture lessons learned, and keep a shared channel for issues and enhancements.
Success Reviews
- Final Acceptance & Success Validation
- Punchlist Walk & Turnover Coordination
- Closeout Documentation, Warranties & Final Finance
- Lessons Learned & Operational Handover Workshop
- Post-Occupancy Support & Issues Channel Setup
Issues & Enhancements
- Draft and distribute the lessons learned report with assigned owners and deadlines.
- Agree on logistics for physical turnover (keys, access, documentation) and subsequent re-inspections.
- Update and circulate the deficiency log with photo evidence and assigned owners.
- Schedule re-inspection dates and identify QA verifier for each remediation.
- Collect and catalog as-built drawings, O&M manuals, warranties, and handover media for transfer.
- Closeout Package Checklist Review
- Confirm all required closeout documents are received and acceptable.
- Agree on warranty responsibilities and contact channels for maintenance issues.
- Authorize or document steps required for final payment and retainage disposition.
- Ensure legal/insurance compliance items are complete for formal closeout.
- Assemble the final compliance and closeout binder and distribute to owner and project archive.
- Issue final payment authorization or list conditional items blocking payment.
- Publish warranty start dates, contacts, and maintenance schedule to the owner and facilities team.
- Project Outcomes Recap
- Produce a prioritized, owner-assigned list of process improvements and actions.
- Complete operational handover plan and training schedule for facilities team.
- Document lessons learned in a shareable format for future project teams.
- Opening & Objectives
- Schedule and prepare operational training sessions for facilities staff.
- Integrate approved process improvements into the firm's preconstruction and site execution checklists.
- Support Model Overview
- Agree on a live, shared channel for reporting issues and enhancements with clear SLAs.
- Schedule and commit to post-occupancy review checkpoints to validate performance over time.
- Ensure owners and contractors are aligned on warranty inspection cadence and responsibilities.
- Create the shared issues channel, configure ticket types/SLA, and invite owner and contractor contacts.
- Publish the post-occupancy review calendar (30/90/180 days) and owners for each checkpoint.
- Document and distribute the escalation contact list and response expectations.
- Confirm which success signals are satisfied and which require remediation.
- Obtain formal acceptance sign-offs or documented conditional acceptances.
- Assign owners and deadlines for any outstanding items required for final acceptance.
- Agree on timeline and responsible parties for closing residual risks and communicating status.
- Compile and distribute the final acceptance package with sign-off fields for the owner.
- Create/update the outstanding items register with owners, due dates, and verification criteria.
- Schedule follow-up acceptance verification/closeout milestone and responsible inspector.
- Safety & Logistics Brief
- Verify and accept completed punchlist items against objective standards.
- Create a prioritized deficiency log with owners and due dates for unresolved items.
- System-by-System Walkthrough
- Warranties, Maintenance & O&M Responsibilities
- Review Success Signals & Acceptance Criteria
- Successes & What Worked
- Shared Channel Configuration
- Challenges & Root-Cause Analysis
- Evidence Package Review
- Final Cost Reconciliation & Change Order Log
- Verify Completed Items
- SLA & Escalation Path Definition
- Deliverable & Turnover Checklist Walkthrough
- Log Remaining Deficiencies
- Post-Occupancy Review Schedule
- Liens, Insurance & Legal Compliance
- Prioritized Improvement Actions
- Warranty Call-back & Preventive Maintenance Plan
- Authorize Final Payment & Retainage Release Steps
- Outstanding Items, Risks & Contingencies
- Turnover Logistics & Artifact Handover
- Operational Handover & Training Needs
- Re-inspection & QA Verification Plan
- Close & Documentation Plan
- Record Retention & Distribution Plan