Capital Project Delivery
Capital-intensive projects where entitlement, financing, construction, and tenancy require multi-party coordination.
Inside this journey
-
Pre-Discovery
Align decision-makers, timeline, and non‑negotiable constraints before deeper discovery.
-
Stakeholder Alignment
Confirm decision roles, board‑approved milestones, the fixed occupancy date, and what ‘must not slip’ for each stakeholder.
Alignment Questions
Starting Together: Tell Us the Big Picture
- In one paragraph, describe this project and the fixed occupancy date that cannot slip.
- What type of facility is this?
- Which of these budget bands best matches your current cost target (including contingency)?
- Which delivery or procurement approach are you currently favoring?
- Who sponsored the project internally (Board, CFO, CEO, Department head, other)? Please name role and, if possible, person.
- Who on your team will be the day-to-day contact for preconstruction and decisions (name, role, preferred contact)?
Who Actually Signs Off When It Matters?
- If one stakeholder could unilaterally delay the occupancy or force a major scope cut, who would it be—and what power do they hold that would allow it?
- For the people listed below, indicate their decision authority and typical reaction to cost vs. schedule tradeoffs.
- Which milestones require board or executive-level sign-off (schematic approval, GMP, financing, occupancy)? Select all that apply and note expected approval windows.
- What is each stakeholder’s single ‘must not slip’ item (e.g., revenue date, clinical accreditation, production ramp)? Please list stakeholder and their non‑negotiable.
- How quickly can final decisions be pulled together if a trade‑off is required (days, weeks)?
The Risk Stories You’ve Lived — And Those You Fear
- What’s one past project close to this size/type that taught your team a harsh lesson—what went wrong and who still remembers it?
- Which of these recurring risk patterns have you experienced or worry will recur on this job?
- How often do project controls (cost/schedule reports) reflect reality on your projects—usually accurate, often optimistic, frequently outdated, or unreliable?
- When a risk materialized previously, how did it feel internally—embarrassment, finger-pointing, calm correction, or financial panic? Tell the story and the human impact.
- Which external constraints (procurement rules, union agreements, bonding limits, grant conditions) could realistically prevent a proposed mitigation from being implemented?
- How much institutional memory do you have for projects like this—do you have post‑mortems, centralized lessons learned, or mostly tribal knowledge?
If Schedule Could Speak, What Would It Demand?
- If the occupancy date slid by one quarter, what concrete business outcomes would be affected (lost revenue, enrollment, production ramp, regulatory deadlines)? Please quantify if possible.
- What tolerance do you have for schedule variance before you trigger executive escalation or contract remedies?
- Which parts of the schedule do you consider absolutely immovable (critical handoffs, phasing for occupied operations, equipment install windows)?
- How do you currently quantify schedule risk and early warning—do you use rolling lookaheads, risk registers with scenario dates, float ownership, or something else?
- If we proposed accelerated structural sequencing that shortens critical path by X weeks but increases near-term cash flow, how would your team evaluate that tradeoff?
Where Baselines Break: Controls, Data, and Assumptions
- What makes your current cost and schedule baseline believable—or not—on day one?
- Which project control tools or systems do you use today for cost/schedule/risk reporting?
- How frequently are cost and schedule forecasts refreshed, and who reviews them?
- Describe one assumption in your baseline that keeps you awake at night—why is it fragile?
- Have you performed independent estimate cross-checks or third‑party schedule reviews during design? If so, what changed as a result?
- Who owns change management and baseline acceptance once construction begins?
How Much Skin Is on the Line? Money, Incentives, and Trust
- If commercial terms shifted to place more at‑risk on the contractor to protect your occupancy and budget, how comfortable would you be with that approach?
- Which fee and incentive structures have you used or considered (fixed fee, guaranteed maximum price, bonuses for early completion, pain/gain share)?
- What bonding and insurance requirements are mandatory for contracts on this program?
- Have prior contracts created perverse incentives (e.g., low fee to win, then maintain scope creep) that you want to avoid? Tell the specific example.
- What governance cadence feels right to you (weekly site meetings, monthly executive reviews, quarterly board updates)?
- What would you see as a fair baseline acceptance threshold for cost and schedule before construction starts (e.g., +/- 3% cost, +/- 30 days)?
A Day in Construction: Phasing, Occupied Ops, and What Never Stops
- Tell us about the occupied operations we must protect—what activities, departments, or processes cannot be disrupted under any circumstances?
- Which logistics constraints are non‑negotiable (site access windows, noise curfews, deliveries through specific gates, contractor parking)?
- How transferable is your facilities staff—can you dedicate existing staff to construction oversight, or will you rely on external O&M consultants?
- Which trades or scopes do you most want the contractor to self‑perform (concrete, structural steel, finish carpentry, MEP, other)?
- When it comes to phasing around occupied spaces, what’s the single biggest worry you have that you’d like us to eliminate?
- Are there hard permit or inspection windows (e.g., life‑safety system tie‑ins) that determine certain work sequences?
What Would Success Look and Feel Like?
- Beyond hitting the occupancy date, what measurable outcomes would make this project a success for you (on-time occupancy, budget tolerance, commissioning acceptance, user satisfaction)?
- What cost tolerance is acceptable before you consider stopping scope versus funding an overrun (percent or dollar value)?
- How do you define acceptable value engineering—what elements can be adjusted and what must be preserved at all costs?
- What owner acceptance criteria will be used at key milestones (substantial completion, commissioning, final closeout)? Please list top 3 criteria.
- How would you like lessons learned and ongoing issue tracking handled post‑occupancy (regular reports, shared channel, scheduled retrospectives)?
- If we delivered the project on time and within tolerance, what would that enable for your organization (revenue, enrollment, production, strategic confidence)?
Red Flags & Deal Killers — Tell Us What Would Make You Walk Away
- What are the absolute non‑starters in a partner relationship for this project (pricing structure, lack of bonding, no self‑perform capability, poor safety record)?
- Has your team previously terminated a contractor or vendor on a similar program? If yes, what specifically triggered that decision?
- Which documents or assurances would give you confidence to proceed to a commercial commit (detailed baseline, bonded GMP, insurance evidence, staffing plan)?
- What unresolved political or organizational issues (internal turf, unions, board concerns) could derail this deal if not surfaced and addressed early?
- If we identify a critical issue in discovery that would increase cost or delay occupancy, how would you prefer we present it—high-level with options, full forensic detail, or staged recommendations?
-
Current State Mapping
Document existing project controls, procurement constraints, subcontractor reliance, and prior risk events that could repeat.
Current State
Project Snapshot — let’s get oriented
- Which best describes this capital program?
- What is the fixed, non‑negotiable occupancy or go‑live date (month/year)?
- What is the board‑approved budget band for construction (hard cost)?
- Who is the single point owner for capital decisions on your side (title/role)?
- Right now, how confident are you that the program will meet both the occupancy date and the approved budget?
If This Slips, What Breaks?
- If the occupancy date moves by 30–90 days, what immediate financial or operational consequences would you face?
- Which of these consequences worry you most and why?
- Have you quantified the dollar or KPI impact tied to a missed date (e.g., monthly revenue loss, delayed grant start)? If so, please give the figure or KPI.
- Which stakeholders will face the most political pressure if the date slips (select all that apply)?
- What contingency plans—if any—have you shared with the board or executive team to address a schedule slip?
Where Things Tend to Falter — Tell Me the True History
- Think about your last major project that struggled—what single event from that program could repeat here if not addressed?
- Which of these past risk events occurred on prior programs (select all that apply)?
- How were those events resolved and how long did recovery take (weeks/months)?
- Where did you see the weakest project controls in past programs (select up to three)?
- During those events, who was responsible for day‑to‑day risk tracking and escalation?
- How much staff turnover occurred during the recovery period, and how did that affect continuity?
What’s Really Locked In — Constraints We Must Respect
- Tell us about any immovable constraints beyond the occupancy date (provocative): what are the true 'red lines' we must never cross?
- Which of these constraints are contractually or politically non‑negotiable?
- Are there board‑approved milestones or funding release dates linked to project performance?
- What internal approval windows or financial close dates create hard procurement deadlines?
- Which internal stakeholders must sign off on major scope or baseline changes (list titles/roles)?
What Are You Willing to Change to Protect the Date?
- If protecting the occupancy date required accepting increased early cost certainty or an at‑risk delivery model, how willing would you be to shift procurement and contracting approach?
- Which contract delivery models are you open to exploring to transfer schedule risk?
- Would you consider embedding preconstruction services (estimating + scheduling in‑house during design) for fee to lock baseline earlier?
- How tolerant are you of at‑risk commitments (liquidated damages, guaranteed dates, shared savings)?
- What internal approvals or policy changes would be required to adopt a more at‑risk model?
Who Really Holds the Keys—Decision Dynamics and Politics
- Who on your team can veto a proposed change that materially protects schedule or budget—and what motivates their veto power?
- Map the decision roles for this program — who signs the cost baseline, who approves change orders, and who accepts final occupancy?
- How fast can those decision‑makers convene for an urgent approval (hours, days, weeks)?
- What forms of communication move them: quick executive summary, data dashboard, in‑person briefing, formal packet?
- Who else outside the owner organization (regulator, funder, tenant) must be consulted before major decisions?
Hidden Constraints — Procurement, Subcontractors, and Long Lead Items
- What single procurement or subcontractor dependency is most likely to derail your critical path if it isn't secured early?
- Which trades or scopes do you expect to self‑perform versus subcontract (select all that apply)?
- Which long‑lead materials or equipment are already on your radar as potential bottlenecks?
- Have you prequalified or held procurement windows with key suppliers/subcontractors?
- Describe your current project controls stack (software, reporting cadence, cost/schedule model fidelity).
- Are there bonding capacity, insurance constraints, or funding covenants that limit how risk can be assigned?
What Would Success Actually Look and Feel Like?
- Beyond 'on time', name the three measurable signals that would make you say, 'They nailed it.'
- Which KPIs matter most to you during delivery (select top three)?
- What is an acceptable final cost tolerance and the maximum allowable value engineering (VE) you will accept without changing core program?
- How should owner acceptance be verified—what documents or tests are required for 'acceptance'?
- Who signs final acceptance and what evidence will satisfy them?
Small Tests, Big Confidence — early proof we can protect your baseline
- What early proof point during preconstruction would make you confident we can hold the baseline (provocative): a guaranteed milestone, a locked long‑lead buy, or a validated critical path?
- Which rapid deliverable would you value most in the first 60–90 days?
- How much access do we need to your internal data, design models, and decision‑makers to run these tests effectively?
- What format and frequency of early reporting would convince your executive team (scorecard, deep dive, workshop)?
- Who must sign off on these early POC deliverables for you to proceed to contract?
What Keeps You Up That We Must Own
- Which single responsibility related to schedule, quality, or safety do you explicitly want the contractor to guarantee?
- Would you expect the contractor to self‑perform concrete/steel and lock crews for critical path work?
- Which of these commercial protections are non‑negotiable for you?
- What governance cadence (executive, steering, operational) gives you comfort, and who should attend each?
- What staffing continuity expectations do you have for project leadership (e.g., single PM through closeout)?
Next Steps — decision map and commitments to move forward
- If we left this meeting with one commitment from you that would materially change risk exposure, what must that commitment be?
- Would you be willing to authorize embedded preconstruction services (estimating + schedule) on a defined fee to begin locking the baseline?
- Who needs to attend a formal kickoff to authorize preconstruction and by when can they meet?
- What documentation, approvals, or deliverables do you need from us to start procurement windows?
- How would you like progress reported back and at what cadence to satisfy your leadership (format and frequency)?
-
-
Outcome Discovery
Define measurable success signals (on‑time occupancy, cost tolerance, acceptable VE limits) and owner acceptance criteria.
Discovery Questions
Opening: Your North Star for Success
- What single outcome—if achieved—would make this entire project feel like an unqualified success to you?
- Which measurable outcomes matter most to you for this program? (select all that apply)
- Which of those outcomes is truly non‑negotiable for your board and executive team?
- If you had to express your top success metric as a single number or date (e.g., occupancy date, % cost tolerance), what is it?
- How would achieving that single metric change the organization's priorities or next steps (e.g., revenue recognition, new hires, program launches)?
Why the Occupancy Date Really Matters
- If the occupancy date slips by one month, what specific financial, operational, or regulatory dominoes start to fall for your organization?
- Which of these drivers make the occupancy date ‘sacred’ for you? (select all that apply)
- Do you have a firm occupancy date in board materials or financial models that cannot slip? If yes, please enter that date.
- What is your tolerance window around that date (choose the range you consider acceptable before it becomes a crisis)?
- If the date were threatened, which mitigation would you prefer first? (select one)
What's Your True Cost Tolerance?
- When leadership hears 'cost tolerance,' do they treat it as a hard cap, a contingency buffer, or a negotiation target for the team?
- What percent of the baseline construction cost is set aside as contingency today (if known)?
- If we encounter cost pressure, which levers should we use first? (rank order in free response)
- How much value‑engineering (VE) can you tolerate before function is compromised? Choose the maximum acceptable VE impact.
- Which program elements are off‑limits for VE (critical to mission) — list by discipline or space type?
Who Will Say 'Yes' at Each Gate?
- If a recommendation trades schedule for cost, who ultimately signs off and what will they insist on seeing to approve it?
- Which roles are decision makers for budget and schedule thresholds? (select all that apply)
- At what dollar escalation does approval move from internal leaders to the board? (choose range)
- Who will accept the final handover from the contractor (title and name if known)?
- How frequently do your governance groups want cost and schedule updates during preconstruction and construction?
Red Lines: What Must Not Slip
- Which single milestone slipping would force you to halt or materially replan the project?
- For each red line you selected, what is the acceptable contingency (days or $) before you escalate to executive leadership?
- Are there contractual penalties or incentives tied to these milestones today (e.g., liquidated damages, incentives)?
- If a red line is at risk, which mitigation sequence would you prefer? (select one)
- Describe a past milestone that nearly slipped — what saved it or what failed?
What Does Owner Acceptance Actually Look Like?
- When the contractor says 'substantial completion,' what concrete evidence will make you sign off immediately rather than delay acceptance?
- Which handover items must be 100% complete at acceptance? (select all that apply)
- What maximum punch‑list percentage or number are you willing to accept at substantial completion?
- Which systems require demonstrated performance metrics prior to occupancy (e.g., ACH, HVAC, power resiliency)? Please list with thresholds.
- Do you require independent verification (third‑party commissioning or testing) for acceptance? If so, which scopes?
Measuring Success: Signals We Can Track
- If you could watch three KPIs on a dashboard every morning to know the project was healthy, which would they be?
- Which reporting cadence would make you feel informed without being overloaded?
- Who should receive the daily/weekly KPIs inside your organization (titles)?
- Are you comfortable with the contractor providing raw data for your internal auditors or do you prefer consolidated reports only?
- What threshold on any KPI should immediately trigger an escalation to leadership? (specify KPI and trigger)
Risk Trade‑offs — What You’d Be Willing to Change
- If you had to choose, would you accept a higher GMP to guarantee the occupancy date, or a lower GMP with schedule risk—and why?
- What premium (approx % of baseline) would you accept to de‑risk schedule to near certainty?
- Are there program elements you would trade or defer to protect the occupancy date? Please name them.
- Have you used schedule‑protecting premiums or phased occupancy on prior projects? If so, what worked and what didn’t?
- What level of contractor at‑risk commitment (e.g., performance guarantees, liquidated damages) would you require to accept a firm occupancy promise?
The Handover Experience You Want
- Does 'ready for occupancy' mean the same thing to your clinical teams, finance team, and facilities ops? Where do definitions diverge?
- Which handover documents are mandatory before staff can operate in the space? (select all that apply)
- How much operational training (hours per discipline) do you expect before occupancy?
- Would you require simulated operations (walkthroughs, mock workflows) as part of acceptance? If yes, which departments must participate?
- What post‑handover warranty or support period do you require to consider the project truly successful?
If We Don’t Align Now, Where Will the Friction Start?
- If we fail to agree on acceptance criteria up front, which stakeholder group will feel the consequences first and why?
- Which areas do you foresee being most contentious during negotiations (select all that apply)?
- What would you need from us in the next 7–14 days to feel confident we share the same success definition?
- Who needs to formally sign or endorse the outcome definitions on your side (list titles/names)?
- On a scale from 1–10, how confident are you today that the project’s key success signals are clear across your leadership team? (1 = not confident, 10 = fully aligned)
Next Steps — Locking the Outcomes into a Baseline
- Assuming we capture these acceptance criteria and KPIs, what is a reasonable internal timeline for your team to review and approve them?
- Who on your team will own maintaining the baseline acceptance criteria once agreed (title/name)?
- Would you like us to draft the measurable acceptance matrix (KPIs, thresholds, verification method) and present it to your governance group?
- What format do you prefer for the acceptance matrix and dashboards? (select all that apply)
- Anything else we should know about how you’ll judge success that we haven’t covered?
-
Solution Experience
Translate the owner’s constraints into a focused scenario showing how embedded preconstruction, self‑perform structural scope, and at‑risk delivery secure schedule and budget outcomes.
Experience Meetings
- Solution Experience: Diagnostic Alignment
- Scenario Design Workshop — Focused Delivery Scenario
- Model Proof — Integrated Schedule & Cost Review
- Stakeholder Validation & Go/No‑Go for Embedded Preconstruction
- Schedule the Solution Scope baseline workshop and Mutual Commit meeting with confirmed governance attendees.
- Owner to confirm 'must not slip' items in writing and identify decision‑makers for gating points.
- Seller to secure provisional crew availability commitments (LOI) for self‑perform concrete and steel for the agreed lock dates.
- Executive Model Walkthrough
- Prove the focused scenario meets the Future State against acceptance metrics under baseline and identified risk cases.
- Obtain owner confirmation (provisional sign‑off) on model assumptions and thresholds to use as a baseline for procurement decisions.
- Identify any remaining open assumptions and assign owners/timelines to close them before Mutual Commit.
- Seller to finalize model assumptions and produce a 1‑page Assumption Register with sources for each key input.
- Seller to create 30/60/90‑day mitigation plans for the top three critical‑path risks.
- Owner to confirm which cost/schedule thresholds require escalation and who has sign authority for VE decisions.
- Prepare a short briefing packet for executives summarizing model proof for the Stakeholder Validation meeting.
- Executive Summary of Proof
- Obtain executive confirmation (provisional or final) that the focused scenario is acceptable to proceed into Solution Scope.
- Collect sign‑offs or assigned unresolved items with owners and deadlines to avoid downstream delays.
- Authorize embedded preconstruction kickoff activities and provisional crew mobilization consistent with the scenario.
- Agree governance cadence and decision rights for the upcoming Mutual Commit stage.
- Circulate signed Acceptance Checklist and record any open questions with owners and target close dates.
- Seller to issue LOIs or provisional mobilization letters for self‑perform crews where authorized.
- Update the integrated model and procurement plan with any decisions made and distribute to stakeholders.
- Welcome & Objectives
- Have a single‑sentence, owner‑validated Current State that everyone can repeat.
- Agree quantified consequences (cost, time, operational impact) tied to the Current State.
- Define a single‑sentence Future State and 3–5 measurable acceptance metrics the Solution Experience must prove.
- Assign prework owners and lock the Scenario Design Workshop date and attendee list.
- Finalize and circulate the one‑sentence Current State and Future State statements to all attendees.
- Owner to provide source documents (budget baseline, milestone schedule, major subcontractor agreements, previous risk events) within 48 hours.
- Seller to prepare consequence calculation summary and required modeling inputs for the Scenario Design Workshop.
- Schedule Scenario Design Workshop and confirm required decision makers (VP Capital, Facilities Director, CFO representative, Estimating, Scheduling, Self‑Perform Lead).
- Recap Preconditions
- Produce one focused delivery scenario with explicit roles, timelines, and decision gates that maps to the Future State.
- Identify the exact preconstruction deliverables and owner inputs required to lock the budget and schedule.
- Agree the self‑perform structural scope and crew lock milestones that control the critical path.
- Outline the at‑risk commercial mechanics and contingency approach to be proven in the Model Proof meeting.
- Seller to build an integrated schedule & cost model of the focused scenario using provided owner data.
- Seller to produce a list of long‑lead procurement items and recommended procurement windows.
- Critical‑Path Sensitivity Analysis
- Current State Statement (single sentence)
- Constraint & Priority Mapping
- Stakeholder Concerns & Validation
- Cost Contingency & VE Tolerance Mapping
- Acceptance Checklist & Sign‑offs
- Consequence Quantification
- Embed Preconstruction Plan
- Risk Scenario Simulations
- Future State Definition (single sentence)
- Authorize Preconstruction Mobilization
- Define Self‑Perform Structural Scope
- Acceptance Metrics & Prework Requirements
- At‑Risk Delivery Mechanics
- Validation & 'Is this what you meant?' Check
- Next Steps to Solution Scope / Mutual Commit
- Draft Focused Timeline & Milestones
- Decisions & Next Steps
- Validation Checks & Decision Gates
-
Solution Scope
Define modules, responsibilities, deliverables, and verification criteria for preconstruction, self‑perform trades, procurement, and program controls.
Scope Configuration
- Cast-in-place structural concrete foundations and slabs
- Formwork, shoring, and falsework installation and removal
- Structural steel erection and connection installation
- Execute concrete post-tensioning and anchorage installations
- Install MEP rough-ins (HVAC, plumbing, electrical)
- Perform field and material testing (concrete, soils, welds)
- Install interior finish carpentry and millwork
- Install temporary infection-control containment systems
- Install temporary site utilities and construction power
- Provide on-site superintendent and daily construction oversight
- Administer subcontractor contracts and process pay applications
- Procure and deliver long-lead equipment and materials
- Perform MEP systems commissioning and start-up
- Produce record drawings and O&M manual turnover packages
Scope Questions
Cast-in-place structural concrete foundations and slabs
- Is cast-in-place concrete foundations and slab work required for this project?
- What is the estimated concrete volume or area (used to size crews and schedule pours)?
- Who is responsible for structural concrete design, mix specs, and reinforcing details?
- Are specialty concrete techniques required (high-strength mix, pumped concrete, additives, or lightweight slabs)?
- What schedule constraints affect concrete pours (seasonal limits, freeze windows, phased occupancy milestones)?
- What acceptance and verification criteria will be used for concrete (compressive tests, flatness/TI, tolerance, survey benchmarks)?
Formwork, shoring, and falsework installation and removal
- Will formwork, shoring and falsework be provided as part of the contract scope?
- What vertical heights or span conditions drive shoring complexity?
- Who provides engineered shoring/falsework designs and PE stamps?
- Are removal windows or sequencing constraints (e.g., progressive removal tied to finishes or openings)?
- How will formwork & shoring interface with concrete pour sequencing and access for trades?
- What verification and acceptance methods are required for temporary works (PE inspection, deflection monitoring, shop drawing approval)?
Structural steel erection and connection installation
- Is structural steel erection included in scope or will it be provided by others?
- Estimate the anticipated steel tonnage or frame complexity for planning cranes and crew size.
- What is the expected mix of bolted vs welded connections and any special connection types (seismic, moment frames)?
- Are there crane, lift or staging constraints (site footprint, critical lifts, night shifts) that will affect erection sequencing?
- Who is responsible for shop fabrication QA/QC and field weld inspection (CWI)?
- What acceptance/tests are required for steel erection and connections (bolted torque records, weld NDT, alignment tolerances)?
Execute concrete post-tensioning and anchorage installations
- Is post-tensioning or specialized anchorage required for slabs or structural elements on this project?
- Who will supply and certify post-tensioning materials and vendors?
- What testing and certification are required (strand proof testing, grouting verification, installation records)?
- What sequencing or cure windows affect when post-tensioning can be executed?
- Who is responsible for long-term monitoring or warranty on post-tensioned elements?
- What interface issues exist with MEP embeds, slab penetrations, or future finishes that require coordination?
Install MEP rough-ins (HVAC, plumbing, electrical)
- Which MEP disciplines are in scope for rough-in work?
- What is the status of MEP design documentation (IFC, permit set, schematic, not started)?
- Who is responsible for procurement of long-lead MEP equipment (chillers, AHUs, switchgear)?
- What access, shutdown or phasing constraints affect MEP rough-in (occupied spaces, night work, infection-control zones)?
- What verification deliverables are required for MEP rough-ins (as-built risers, load calculations, conduit pull testing)?
- Is pre-functional testing or partial commissioning required during rough-in?
Perform field and material testing (concrete, soils, welds)
- What testing program level is required for the project?
- Who will engage and approve the testing agency (GC-selected, owner-selected, third-party mandated)?
- What reporting cadence and format are required for testing results?
- Are specialized tests required (geotechnical instrumentation, weld NDT, corrosion potential)?
- Are there acceptance criteria or hold points tied to test results that will stop work if failed?
- Are on-site lab facilities or accelerated testing required to meet schedule?
Install interior finish carpentry and millwork
- Which finish carpentry scopes are required (casework, doors/frames, trim, custom millwork)?
- Who provides shop drawings and mock-ups for custom millwork and finish carpentry?
- What finish standards or material specifications must be met (wood species, veneers, hardware grades)?
- What are the sequencing constraints relative to MEP, drywall and painting for installation?
- What verification / acceptance methods will be used (mock-up approval, punchlist, final owner sign-off)?
- Are special storage/protection conditions required for millwork prior to installation (humidity control, covered storage)?
Install temporary infection-control containment systems
- Is temporary infection-control containment required for any phase or area of work?
- Which infection-control standards must containment meet (CDC, local health authority, owner-specific protocols)?
- Is negative pressure or HEPA filtration required inside temporary containment?
- Who will monitor and certify air quality and containment integrity during construction?
- What decommissioning and cleaning acceptance criteria are required before handing areas back to owner?
- How long will containment systems be required and are phased removals expected?
Install temporary site utilities and construction power
- What temporary power capacity and distribution is required for construction?
- Will temporary water, sanitary and temporary sewer connections be required on site?
- Who is responsible for utility fees, metering and permanent utility coordination?
- Are temporary transformer / substation / generator solutions required for phased power?
- What schedule or sequencing constraints affect utility activation (city tie-in windows, permitted work hours)?
- What verification / inspection is required by the utility provider or authority having jurisdiction?
Provide on-site superintendent and daily construction oversight
- What level of on-site supervision is required (full-time superintendent, part-time, project manager oversight)?
- Are there required qualifications or experience (healthcare projects, occupied campus experience, union familiarity)?
- Do you require named personnel guarantees or continuity assurances for key site staff?
- What reporting cadence and format do you expect from site oversight (daily logs, weekly dashboards, safety reports)?
- Will the superintendent be responsible for safety oversight and toolbox talks or is a dedicated safety officer required?
- Will the superintendent manage subcontractor coordination, scheduling and interface meetings?
-
Mutual Commit
Finalize commercial terms, bonding and insurance requirements, fee alignment, governance cadence, and baseline acceptance for cost and schedule.
Agreement Modules
- Statement of Work (SOW)
- Master Construction Agreement (CMAR/GC Contract)
- Commercial Terms & GMP Confirmation
- Fee Schedule & Payment Terms
- Bonding & Performance Security
- Insurance Requirements & Certificates
- Baseline Acceptance (Cost & Schedule)
- Governance, Reporting & Meeting Cadence
- Change Order & Value Engineering Protocol
- Mobilization / Notice to Proceed (NTP)
- Self-Perform & Critical Trade Commitments
- Risk Allocation & Contingency Protocol
- Commissioning, Acceptance Testing & Turnover Criteria
- Warranties, Maintenance & Closeout Obligations
- Dispute Resolution & Termination Terms
- Authorized Signatories & Execution Checklist
-
Deployment
Operationalize rollout with readiness checks, enablement, and outcome validation.
-
Pre-Deployment Readiness
Confirm staffing continuity, procurement lead times, permits, site access, and phased logistics for occupied operations before mobilization.
Readiness Questions
Project Snapshot: Quick Orientation
- What is the project name, your organization, the fixed occupancy date, and the phase we are in today?
- Which building type best describes this work?
- Which delivery method and commercial structure is currently planned or in place?
- What size band describes the total project construction value?
- Who on your side is the single point of accountability for program decisions and baseline acceptance?
If Key People Walked Tomorrow, Would We Notice?
- Imagine your project director or facility lead left six weeks before mobilization—what immediate gaps would that create?
- Which roles are mission‑critical for a seamless deployment and who are the current named individuals?
- Do you have confirmed backups or transition plans for each critical role listed?
- How stable has your staffing been on recent large projects—any pattern of last‑minute departures or turnover we should know about?
- If continuity risk materializes, how quickly can your organization appoint a replacement or approve an external partner to fill the role?
- How would losing a key internal person make you feel about meeting the occupancy date—confident, worried, or urgent? Explain briefly.
Which Procurement Lead Times Are We Underestimating?
- If a single long‑lead item slips six weeks, which procurement item would cause the largest schedule cascade?
- Please list the top 6 long‑lead items you currently expect on this project (include vendor names if known).
- For each long‑lead item you named, what is the procurement route and current estimated lead time?
- Have you experienced procurement hold‑ups on past projects from the same suppliers or market? If yes, describe one example and its impact.
- What level of contingency do you currently plan to hold on long‑lead items (schedule buffer and cost contingency)?
- Would you consider vendor lock‑ins and early buyouts to protect the critical path? If yes, which packages are highest priority?
Are Permits a Paper Chase—or a Schedule Hammer?
- If permitting took twice as long as expected, what part of the schedule or budget would it most threaten?
- Which permits and regulatory approvals are critical before any site work can begin?
- What is the current status and estimated review time for each major permit you listed?
- Have you had prior projects delayed by municipal or agency reviews? Tell us one story—how long was the delay and what caused it?
- Who is the agency contact or permit expeditor you currently work with, and what leverage do they have to accelerate approvals?
- Would you be open to targeted pre‑submittal reviews or agency engagement sessions to reduce unknowns? (This is different from full permitting.)
How Will the Site's Daily Life Actually Work?
- If construction begins while operations stay live, what single site constraint would be most disruptive to ongoing operations?
- Which zones will remain occupied and what are their peak activity periods we must protect?
- Do you have an initial phasing strategy for occupied operations (describe phases and approximate durations)?
- What site access controls, credentialing, and infection control protocols do contractors need to follow on day one?
- How do you prefer deliveries and material staging to be managed on constrained days—scheduled windows, off‑site staging, or night/weekend deliveries?
- Share one recent example where a site logistics decision either protected or disrupted operations—what happened and what did you learn?
What's Already Non‑Negotiable?
- If we had to protect three immutable project constraints right now, which would they be (rank or list)?
- What cost tolerance exists before the owner directs value engineering, and what parts of scope are off limits for VE?
- Are there any contract provisions, board conditions, or external funding deadlines that make certain dates or costs legally non‑negotiable?
- Who from the owner's side must sign off on baseline acceptance for schedule and budget, and what is their decision timeline?
- If a late‑breaking scope change is requested, what governance process would you expect to evaluate its impact?
What Keeps You Up at Night — Real Risks & Past Repeats
- Which single past project failure or near‑miss would you most want to avoid repeating here?
- Have you experienced repeated vendor or subcontractor failures on similar projects? If yes, which trades or packages are highest risk?
- How do you currently track and escalate emerging risks—who gets alerted and at what thresholds?
- Which project controls tools or reports do you rely on today, and where do they fall short?
- What would a successful mitigation look like for your top risk—timing, ownership, and acceptable cost to resolve?
Ready to Mobilize? Decision Gates & Quick Wins
- What single go/no‑go trigger would make you pause mobilization even if everything else seems ready?
- Which three items on a pre‑deployment checklist give you the most reassurance (e.g., bonded crews locked, permits in hand, deliveries staged)?
- What contingency triggers (time or cost) should automatically shift us into an accelerated mitigation mode?
- Who must attend the pre‑mobilization governance call and who has authority to greenlight mobilization?
- If we prioritize three quick wins in the next 30 days to harden readiness, which would you choose from this list?
- Realistically, how soon can we run a joint pre‑deployment readiness review (date or timeframe)?
-
Deployment Enablement
Sequence critical‑path work, assign owners, lock self‑perform crews for concrete/steel, and execute phased construction with clear checkpoints.
-
Validation Checklist
Verify milestone acceptance, commissioning plans, contingency triggers, and readiness for the non‑negotiable occupancy date.
Validation Questions
Quick Snapshot — Where We Start Together
- Which of these best describes the project we’re talking about?
- What is the board‑approved occupancy date (MM/YYYY) or the fixed milestone we cannot miss?
- What is the current baseline construction budget (or budget range) we should use for early alignment?
- Who holds final sign‑off for budget and occupancy decisions? Name role(s) and whether they are internal (Owner) or external (Board/Trustees).
- Why is this date non‑negotiable? (e.g., revenue recognition, enrollment start, production ramp, lease start)
If This Project Slid One Day, Who Would Notice First?
- If the schedule slipped by 60 days, which stakeholder would feel the impact first and how?
- Which internal groups have veto power or hard constraints (Facilities, Clinical Ops, IT, Regulatory, Finance, Academic Affairs)?
- Has your governance body set milestone 'must not slip' dates for multiple stakeholders? If so, where are the most fragile handoffs?
- How emotionally or politically sensitive is missing this occupancy date inside your organization? (share concrete consequences or prior examples)
- Who in your team we should consider a champion for change versus a pragmatic skeptic we need to win over?
Where Budget and Reality Keep Missing Each Other
- When you look back at recent projects, what are the top causes of cost growth you’ve actually experienced (procurement, scope gaps, latent conditions, VE, owner change)?
- How accurate have your preconstruction estimates been on comparable projects (variance to final GMP or final cost)?
- Tell us about a recent risk event that repeated across projects—what happened and how long did the recovery take?
- What procurement constraints or internal policies (e.g., mandatory competitive bid, preferred subcontractor lists, union rules, bonding thresholds) will shape how we source trade work?
- How comfortable are you with an at‑risk delivery model where the contractor self‑performs critical structural scope and carries schedule/cost responsibility?
What’s Getting in the Way of Predictable Schedules?
- We often see critical‑path control through who controls concrete/steel—who currently owns the structural scope and schedule levers on your program?
- Have phased occupancy or occupied‑campus logistics been required? If yes, where have the toughest interfaces been?
- How do you currently verify milestone acceptance and owner acceptance criteria—are punch lists, commissioning, and OT/IT handoffs centralized or fragmented?
- Which permit or long‑lead items have the highest risk of delaying mobilization (e.g., MEP interfaces, specialty equipment, approvals)?
- When schedule pressure mounts, where does the organization tend to make compromises—and with what consequences?
What Would On‑Time, On‑Budget Really Mean to You?
- If the project hit the occupancy date and budget baseline exactly, what practical outcomes would that enable for your organization?
- What are your measurable success signals for acceptance (e.g., commissioning test pass rates, percent of punch completed, patient flow readiness)?
- What is your acceptable cost tolerance before you require formal change control or board notification (percentage or dollar threshold)?
- How far can value engineering erode program function before it becomes unacceptable? Describe must‑keep elements versus negotiable items.
- Who will sign final owner acceptance—name role(s) and any departmental checklists they require?
If We Designed the Delivery Around Your Constraints, What Would Change?
- Which of these delivery features would be highest value to your team: embedded preconstruction estimating, self‑perform structural crews, guaranteed schedule milestones, or integrated commissioning?
- How important is continuity of personnel (estimating, PM, superintendent) to you, and how long would you expect core team members to stay engaged?
- If we proposed locking self‑perform crews on the critical path, what concerns would you want us to address first (cost certainty, bonding, safety, schedule control)?
- What reporting cadence and level of detail does your governance team require during preconstruction and into construction (weekly schedule, earned value, risk register)?
- What would make you trust an external construction partner enough to give them authority over schedule levers?
Commissioning, Contingency, and the Final Gate
- What commissioning standards and acceptance tests must be complete to declare the space ready (e.g., clinical equipment integration, HVAC balancing, IT systems)?
- How do you prefer contingency to be managed—pooled owner contingency, contractor contingency in GMP, or a hybrid approach?
- What contingency triggers should automatically prompt executive escalation (e.g., >X days delay, >Y% cost exposure, critical equipment delivery miss)?
- Who leads commissioning and acceptance on your side (Facilities, Clinical Engineering, IT), and who will be our daily point of contact for readiness signoffs?
- Are there occupancy phasing priorities (which areas must be ready first) and non‑negotiable handover sequences we should plan around?
What Would Make You Say Yes to Moving Forward?
- What commercial alignments would you require to feel comfortable (shared savings, GMP with open books, fixed fee, milestone payments)?
- What bonding, insurance, or contract assurances are mandatory for your procurement team before awarding a construction contract?
- What governance cadence would you prefer during construction (weekly operational, monthly executive, quarterly board updates)?
- What would be a reasonable small‑step pilot (deliverable in 30–90 days) that would demonstrate our ability to lock budget and schedule before full commitment?
- Is there anything we haven’t asked that, if we understood it now, would change how we approach your project?
-
-
Success
Review outcomes against the agreed baselines, capture lessons learned, and maintain a shared channel for issues and enhancements.
Success Reviews
- Final Baseline Review & Acceptance
- Performance & Metrics Review (Project KPIs)
- Lessons Learned Workshop — Cross-Functional
- Warranty, Post-Occupancy Support & Issues Channel Setup
- Continuous Improvement Governance & Program Transfer
Issues & Enhancements
- Agree the process for evaluating and prioritizing enhancement requests separate from warranty.
- Create corrective action owners with deadlines for systemic issues (procurement lead time, scope gaps, staffing continuity).
- Log safety incident follow-ups and responsible parties for any outstanding compliance items.
- Context & Workshop Rules
- Produce a prioritized, owner-assigned Lessons Learned backlog ready for governance review.
- Ensure lessons are specific, evidence-backed, and linked to measurable outcomes to avoid generic recommendations.
- Establish the cadence and owner for tracking implementation of improvements.
- Publish the prioritized Lessons Learned backlog to the shared channel with owners, target dates, and acceptance criteria.
- Schedule the first Improvement Governance check-in to review progress on top 3 backlog items.
- Assign subject matter leads to prepare brief SOP/upgrade proposals for any systemic processes to be changed.
- Open Issues & Warranty Log Review
- Establish a single shared channel and a clear ticketing workflow for post-occupancy issues.
- Assign RACI and SLAs for warranty response and escalation to ensure timely resolution.
- Welcome & Objectives
- Configure and seed the shared channel/ticketing system with current open issues and assign initial owners.
- Publish the Warranty RACI and SLA document to the project archive and notify stakeholders.
- Schedule training sessions for owner maintenance staff and confirm attendance lists.
- One-Sentence Future State
- Establish a clear governance cadence and KPI set to monitor adoption of lessons in future programs.
- Agree ownership for each improvement backlog item and confirm transfer of program artifacts.
- Create a measurable feedback loop so future projects demonstrate reduced occurrences of the same failures.
- Finalize and distribute the Continuous Improvement Governance charter with meeting cadence and KPIs.
- Schedule knowledge transfer workshops and assign artifact owners for delivery.
- Publish a 12-month improvement roadmap showing milestones for top-priority backlog items.
- Obtain formal acceptance of cost and schedule baselines or document agreed exceptions.
- Clarify and assign ownership for outstanding closeout tasks required to finalize project records.
- Ensure the executive steward and project sponsor understand and approve final variances and their consequences.
- Produce a signed Baseline Acceptance record capturing accepted baselines and exceptions.
- Assign and schedule closure of outstanding deliverables (warranties, as-builts, final payments) with target dates.
- Circulate final variance dashboard and supporting backup to governance stakeholders within 3 business days.
- Pre-meeting Data Checklist
- Confirm where performance met or missed baselines with evidence from controls systems.
- Identify root causes for major variances and translate them into concrete corrective actions.
- Capture metrics and narrative needed for the lessons-learned workshop.
- Deliver a consolidated Project Performance Pack (EVM, schedule charts, commissioning summary) to the lessons-learned team.
- Baseline Recap
- RACI for Warranty & Defects
- Successes That Should Repeat
- Schedule Performance Analysis
- Governance Cadence & KPIs
- Improvement Backlog Handover
- Shared Channel + Ticketing Workflow
- Cost & Earned Value Analysis
- Failures & Root Causes
- Executive Variance Summary
- Quality, Commissioning & Acceptance Metrics
- Knowledge Transfer & Artifacts
- Breakout by Domain
- Enhancement Requests Process
- Detailed Variance Review
- Safety and EMR Summary
- Handover & Training Requirements
- Synthesize & Prioritize Backlog
- Measurement & Continuous Feedback Loop
- Acceptance Decisions & Exceptions
- Root Cause & Corrective Actions
- Validation & Close
- Next Steps for Closeout Deliverables