Industrial & Manufacturing Oil, Gas & Natural Resources Exploration & Production

Subsea Systems

Capital-intensive extraction and processing programs where safety, regulation, and supply chain complexity define execution.

TechnipFMC Subsea 7 Saipem Baker Hughes
Inside this journey
  1. Pre-Discovery

    Align the room on outcomes, decision process, and constraints before deeper discovery.

    1. Stakeholder Alignment

      Confirm decision roles, approval timeline, weather-window constraints, and each stakeholder’s definition of ‘on-time, low-risk delivery.’

      Alignment Questions

      Getting to Know the Team and Timeline

      • Who from your organization will be directly involved in selecting and approving the subsea production system (names and roles)?
      • Which of these roles best describes the primary sponsor for the procurement decision? Options: Project Director, Subsea Engineering Manager, VP Development, Procurement Lead, Technical Authority, Other
      • What is the target first‑oil date we should be designing the delivery schedule around? Options: Provide a specific date (enter below), +/- range within 3 months, +/- range within 6 months, Flexible/undetermined
      • Please enter the specific date or range for the first‑oil target (if known).
      • How confident is the core team that the current project timeline will hold through installation? Options: Very confident, Moderately confident, Uncertain, Low confidence
      • Who is the single point of contact we should escalate schedule or technical clarifications to?

      Are We All Using the Same Definition of 'On‑Time'?

      • Which stakeholder in your group would most strongly disagree with your current definition of ‘on‑time, low‑risk delivery’ and why might they disagree?
      • For each stakeholder listed, what does ‘on‑time delivery’ mean in practical terms (e.g., delivery to yard, FAT complete, onsite ready for loadout)? Options: Delivery to fabricator/yard, FAT & system integration complete, Shipped and in transit, Delivered to port for loadout, Installed on host, Commissioned and producing
      • How does each key stakeholder define 'low‑risk'—is it schedule certainty, minimal interventions, warranty terms, or something else? Please map stakeholders to their top priority.
      • Are there any non‑negotiable contractual or regulatory milestones that must be met to satisfy a stakeholder’s definition of ‘on‑time’? Options: Investment committee sign‑off, Regulatory permits, Host facility ready for tie‑in, Vessel booking confirmed, Financing close, None
      • If stakeholders’ definitions conflict, which group's definition typically takes precedence and why? Options: Investment/Exec Committee, Project Director, Subsea Engineering, Procurement/Commercial, Regulator, Other

      Invisible Deadlines: The Approvals That Kill Schedules

      • Which hidden or informal approvals have historically derailed your project timelines (e.g., third‑party certifier, host engineering sign‑off, finance gates)? Options: Third‑party certification, Host facility engineering sign‑off, Final HSE approvals, Financing/investor approval, Local content/government review, Other
      • How long do each of those approvals typically take from submission to sign‑off in your experience? Options: <2 weeks, 2–6 weeks, 6–12 weeks, 3–6 months, Varies greatly / unpredictable
      • Which internal governance gates (e.g., FEED approval, PCI, gate reviews) are scheduled before contract award and what are their dates?
      • Is there a single approval or external dependency that, if delayed two weeks, would force the installation campaign to slip a season? Options: Yes — please specify (enter below), No
      • If yes, please name that dependency and describe why a two‑week slip is critical.

      Weather Windows and the Cost of a Missed Season

      • Imagine the installation weather window moves by a season — who on your team would bear the biggest political or financial pain, and how would they describe it?
      • What are your preferred and absolute‑latest installation windows (months/seasons), and how flexible are they? Options: Preferred season (enter below), Acceptable window +/- 2 weeks, Acceptable window +/- 1 month, Absolute latest date (enter below)
      • How long can the project absorb a slippage in installation before first oil is deferred by a year or more? Options: <1 month, 1–3 months, 3–6 months, >6 months
      • Do you have contracted vessel or installation assets already booked? If yes, what are the cancellation/change penalty triggers? Options: Yes — high penalty, Yes — moderate penalty, Yes — low penalty, No vessels booked yet
      • What is the estimated daily or weekly cost exposure if the installation campaign is delayed (ballpark)? Options: < $100k/day, $100k–$250k/day, $250k–$500k/day, > $500k/day, Don't know / prefer not to say

      Who Owns the Interfaces — And Where Do They Break?

      • Pick one interface you expect to be the most contentious (supplier↔SURF contractor, SURF↔host, supplier↔host) and tell us why it worries you. Options: Supplier ↔ SURF contractor, SURF contractor ↔ Host facility, Supplier ↔ Host facility, Multiple / all of the above
      • For the following interfaces, who currently owns design responsibility and who owns installation responsibility? (Select all that apply.) Options: Supplier owns design, SURF contractor owns design, Host owns design, Supplier owns installation, SURF owns installation, Host owns installation, Shared / TBD
      • Do you have a current RACI or interface matrix we can review, and when was it last updated? Options: Yes — uploaded and current, Yes — exists but outdated, No RACI exists, Partial RACI exists
      • How have interface disagreements been resolved in past projects—formal change control, executive escalation, or informal compromise? Options: Formal change control, Executive escalation, Informal compromise, Mediation/third party, Other
      • Are there technical interfaces (electrical, control, mechanical) where you require our vendor to absorb responsibility rather than share it? Please specify which and why.

      What Trade‑Offs Would You Make to Protect the Schedule?

      • If you had to choose today: accept a small schedule acceleration with higher technical risk, or protect technical margins and accept a longer manufacturing lead time—what would you pick and why? Options: Protect schedule (accept more technical risk), Protect technical margins (accept longer lead time), Depends on specific subsystem, Undecided
      • What level of long‑term reliability do you require from equipment (e.g., 25‑year mean time between major interventions at 15k PSI)? Options: 25‑year reliability required, 20‑year acceptable, 15‑year minimum, Specify other (enter below)
      • What is the maximum acceptable probability of an unplanned subsea intervention in the first 10 years (as a percentage)? Options: <1%, 1–3%, 3–5%, >5%, Unknown / no target
      • Would you pay a premium to de‑risk schedule via vertical integration and controlled manufacturing lead times? If so, what premium range is reasonable? Options: No premium, Small premium (1–3%), Moderate premium (3–7%), Significant premium (>7%), Depends on guarantee terms
      • If we proposed staged deliveries (critical long‑lead items first), what contractual milestones would you expect tied to those shipments? Options: Partial acceptance and payment, Performance guarantees, Warranty start tied to final installation, Other — describe below

      What Happened Last Time That You Never Want Repeated?

      • Tell us about a prior subsea procurement where schedule or reliability failed—what went wrong and who bore the consequences?
      • Which vendor behaviors during that project reduced your trust the most (e.g., missed comms, hidden schedule slips, quality rework)? Options: Poor communication, Hidden schedule slips, Quality issues / rework, Scope creep without cost control, Failure to manage interfaces
      • How do you usually validate a vendor’s manufacturing and testing claims—factory audits, reference visits, third‑party witness, document review? Options: Factory audit, Reference operator visit, Third‑party witness at FAT, Document & test evidence, Other
      • What evidence would convince you that a vendor’s delivery credibility is high enough to base your installation campaign on their schedule? Options: Recent similar project on‑time delivery, Reference operator endorsement, Detailed integrated master schedule, Financial/insurance backstop, Other
      • Are there specific suppliers, yards, or yards' constraints you prefer or want to avoid? Please explain.

      Governance, Communication Rhythms, and Decision Speed

      • What governance cadence has the best chance of keeping decisions moving—weekly tactical calls, biweekly steering, monthly exec reviews, or another rhythm? Options: Weekly tactical, Biweekly project team, Monthly steering, Ad hoc as needed, Other
      • Who has the authority to approve design changes that affect the manufacturing critical path, and what is the expected approval turnaround time?
      • If an urgent schedule risk emerges, what escalation path do you want us to use (technical lead → project director → executive sponsor)? Options: Technical lead → Project Director, Project Director → Executive Sponsor, Direct to Executive Sponsor, Use existing PMO escalation
      • Which communication formats do stakeholders prefer for progress updates (dashboard, formal minutes, short highlight emails, or live review)? Options: Dashboard, Formal minutes, Highlight emails, Live review sessions, Combination
      • Are there decision blackout periods (e.g., holidays, board months) when approvals typically stall? Options: Yes — specify (enter below), No
      • If yes, please list those blackout periods and any special instructions for urgent approvals.

      Commitments, Remedies, and What 'Mutual' Actually Means

      • What contractual remedies do you expect if supplier delivery causes installation slip (LDs, schedule recovery plan, supplier‑funded offshore support)? Options: Liquidated damages, Schedule recovery obligations, Supplier funded contingency services, Shared risk approach, Other
      • Would you prefer a firm price with tight delivery guarantees or a flexible price with shared risk on schedule? Why? Options: Firm price, tight delivery, Flexible price, shared risk, Hybrid — define milestones, Undecided
      • What governance structure do you expect to resolve disputes quickly (joint steering committee, independent adjudicator, executive committee)? Options: Joint steering committee, Independent adjudicator, Executive committee, PMO mediated
      • Which milestone(s) would you require before issuing a purchase order or moving to detailed design? Options: FEED complete, Commercial terms agreed, Schedule baseline accepted, Regulatory permits in place, Funding closed
      • Are there specific acceptance, test or warranty metrics you require to be contractually guaranteed (e.g., FAT criteria, reliability targets)? Please list.

      Quick Evidence Check: What We Should Review Together

      • Which of these documents can you share with us to accelerate alignment (choose all that apply)? Options: Integrated project schedule (IMS/Gantt), RACI / interface matrix, Approval gate calendar, Weather window and vessel bookings, Technical specs / FEED outputs, None / not available
      • Please upload or indicate where we can access the most current integrated schedule or note if you prefer to walk it through live. Options: Will upload, Share link, Prefer live walkthrough, Not available
      • Who on your team should attend an initial alignment workshop to finalize decision roles and approval timelines?
      • How soon would you be ready to hold that alignment workshop? Options: Within 1 week, Within 2–4 weeks, 1–2 months, Later / not sure
      • Is there anything else—political, technical, or commercial—that would materially change how we approach your delivery schedule?
    2. Current State Mapping

      Document existing project schedule, long‑lead items, vendor performance history, integration points with SURF/FPU, and primary failure modes.

      Current State

      Opening Snapshot — A Quick Project Reality Check

      • Which phase best describes where your project sits today? Options: Pre-FEED, FEED underway, FEED complete / awaiting sanction, Sanctioned — detailed design, Manufacturing started, Fabrication complete / testing, Ready for shipment
      • Please list the top 4 milestone dates (sanction, manufacturing start, shipment window, first-oil) and the single date you cannot miss without severe cost or schedule impact.
      • What is the formal installation weather window and how firm is that window? Options: Fixed and contractually constrained, Guideline with some flex, Tentative / under review, Not defined yet
      • Who on your team owns the subsea equipment delivery schedule and who owns installation campaign coordination (name, role, and contact preference)?
      • On a scale of confidence, how would you rate your current on-time delivery probability for subsea equipment? Options: >90% confident, 75–90% confident, 50–75% confident, <50% confident, Unsure

      If This Ship Misses the Weather Window — What Are We Really Afraid Of?

      • If the subsea deliveries slip beyond the planned weather window, what are the most serious business outcomes you expect? Options: 1-year campaign delay, > $100M cost overrun, Host facility idle time, Regulatory / contractual penalties, Loss of license to operate, Re-sequencing drilling schedule
      • Quantify the financial exposure or schedule slip that turns a delivery delay into an existential problem for the project (estimate or range).
      • What are the non-financial consequences (reputation, stakeholder confidence, regulatory timelines) that worry you most if the installation is missed?
      • What contingency plans would you trigger if a key delivery missed the weather window (defer installation, charter additional vessel, compress commissioning, other)? Options: Defer installation to next season, Charter additional vessel(s), Compress commissioning activities, Split campaign across windows, Negotiate schedule with host/contractor, Other
      • How quickly do you need an accurate root-cause and remediation plan from your supplier after a delivery slip to consider the situation under control? Options: Within 24 hours, 48–72 hours, One week, Two weeks

      Who Holds the Keys — Decision, Approvals, and the Politics of Schedule

      • If delivery dates become negotiable, who has final authority to approve schedule trade-offs (names/roles from owner, procurement, project, operations)?
      • How does your internal approval timeline for scope or design changes typically compare to manufacturing lead times (faster, aligned, or slower)? Options: Faster than manufacturing, Roughly aligned, Slower — approval is a bottleneck, Variable / project-dependent
      • Who are the external parties (SURF contractor, FPU owner, host integrator) that must sign interface deliverables before shipment, and what are their typical response times?
      • When schedule pressure rises, who within your organization is usually empowered to accept increased technical or commercial risk to meet dates? Options: Project Director, VP Development, Procurement Lead, Operations Manager, Joint-venture committee, No single empowered owner
      • Describe a past decision where schedule pressure forced a compromise—what was traded, who pushed for it, and what was the outcome?

      Hidden Long‑Lead Risks We Can’t Afford to Ignore

      • Which components on your bill-of-materials are long‑lead today (for example: Christmas trees, high‑pressure valves, forged bodies, control-module semiconductors, umbilicals)? Options: Subsea trees, Manifolds, High-pressure valves, Forged bodies, Control electronics, Umbilicals / termination assemblies, FCP / control pods, Other
      • For each critical long‑lead item listed, what is the latest acceptable procurement / hold point to keep the manufacturing critical path intact?
      • Which long‑lead items do you currently have purchase orders for, and which are still subject to lead-time negotiation? Options: All critical POs issued, Most issued, a few pending, Key long‑lead items pending, No long‑lead POs issued
      • How resilient is your plan to supply‑chain disruption (dual sourcing, buffer inventory, expedited options)? Options: High resilience (multiple sources), Moderate (some alternatives), Low (single-source dependency), No plan / unknown
      • If a specific long‑lead vendor cannot deliver on time, how do you prefer we handle substitution or redesign decisions (rapid ECR, approved vendor list, joint impact assessment)? Options: Rapid ECR with 48–72h decision, Use pre‑approved alternate vendors, Joint impact assessment then executive decision, Prefer to wait for original vendor

      When Vendors Didn’t Deliver — Stories that Still Sting

      • Tell us about a recent project where vendor delivery or quality issues created major schedule or reliability problems—what happened and what was the root cause?
      • How do you currently measure vendor performance on subsea packages (on‑time delivery, quality NCRs, testing pass rates, technical backlogs)? Options: On‑time delivery, Quality / NCR count, FAT/HIL success rate, Engineering change frequency, Claims / disputes history, Other
      • Which vendor performance issue worries you the most going into manufacturing (engineering rework, shop capacity, test failures, supply-chain shortfalls)? Options: Engineering rework, Shop capacity constraints, Test failures at FAT/HIL, Supply-chain shortages, Logistics/transport delays
      • What remedies or contractual levers have worked for you in the past to accelerate recovery when a vendor slipped? Options: Liquidated damages, Supplier recovery plans, Vendor performance bonds, Fast-track additional resources, Joint steering committee
      • How transparent are your current vendors about lead times and capacity (openly share calendars, intermittent updates, opaque/unreliable)? Options: Open and proactive, Reactive but adequate, Opaque/unreliable, Unknown

      Where Systems Meet—and Systems Often Break

      • What are the primary integration points between your subsea equipment and SURF/FPU systems (electrical control, hydraulic interfaces, mechanical connectors, software APIs)? Options: Electrical control / umbilical, Hydraulic actuation interfaces, Mechanical wet‑mate connectors, Flowline / riser interfaces, Control system software/API, Instrumentation / sensors
      • Which interface has historically caused the most disputes or rework on your projects? Options: Mechanical connectors, Electrical/harnessing, Hydraulic interfaces, Control software integration, Testing acceptance criteria
      • Who is formally responsible for each interface sign‑off (supplier, SURF contractor, host OEM), and are those responsibilities documented in interface control documents (ICDs)? Options: Clearly documented and owned, Documented but not enforced, Informally agreed, Not documented
      • What is your current plan for interface verification (joint FAT/HIL, onshore integration, on‑vessel pre‑lay tests) and where are the gaps? Options: Joint FAT/HIL planned, Separate vendor FAT then integration, On‑vessel pre‑lay tests only, No clear verification plan
      • How do you prefer to resolve interface mismatches discovered late in the program (technical working group, executive escalation, third‑party adjudication)? Options: Technical working group, Executive escalation, Contractual mediation, Third‑party review

      Worst‑Case Failure Scenarios — Let’s Imagine the Headlines

      • If we assume a severe subsea failure after installation, what single outcome would be the worst for your organization (long intervention, production loss, safety incident, regulatory action)? Options: Extended intervention campaign, Major production loss, Safety/environmental incident, Regulatory / license issues, Severe reputational damage
      • What are the primary failure modes you worry about for your subsea architecture (leakage at connector, valve seizure, control electronics failure, manifold structural fatigue)? Options: Connector leakage, Valve seizure/failure, Control electronics failure, Manifold/structural fatigue, Umbilical damage, Other
      • How frequently have you experienced each of these failure modes on prior projects (never, rare, occasional, recurring)? Options: Never, Rare, Occasional, Recurring
      • What mitigations do you currently rely on to reduce intervention risk (redundancy, conservative design margins, accelerated HIL testing, spares strategy)? Options: Redundancy, Conservative design margins, Accelerated HIL/FAT testing, Onshore integration testing, Strategic spares, Rapid intervention contracts
      • If a failure mode did emerge in the field, what would you want your supplier to deliver first—root-cause analysis, temporary bypass solution, expedited replacement hardware, or on-site support? Options: Root‑cause analysis, Temporary bypass solution, Expedited replacement hardware, On‑site technical support

      Testing, Inspection and Acceptance — Where Confidence Is Earned or Lost

      • What FAT/HIL and acceptance tests are critical for you to sign equipment off for shipment, and which are not negotiable? Options: Full system FAT/HIL, Pressure testing at rated PSI, Software-in-the-loop validation, Mechanical proof-loads, Witnessed testing by owner
      • How strictly do your acceptance criteria map to 25‑year reliability expectations (do you require accelerated life testing, vendor reliability data, field performance references)? Options: Require accelerated life testing, Require field performance references, Accept vendor reliability data, Combination
      • Who must be present or grant final acceptance at FAT/HIL (owner team, third‑party inspector, SURF representative)? Options: Owner team, Third‑party inspector, SURF representative, Vendor QA lead, Other
      • What documentation do you require with delivered equipment (test certificates, traceability, maintenance procedures, interface drawings)? Options: Test certificates, Material traceability, Maintenance & spare parts lists, Interface drawings / ICDs, Software revision control
      • If a test fails at FAT/HIL, what governance do you expect for remediation (joint corrective action plan, vendor redesign, executive review)? Options: Joint CAP with timeline, Vendor redesign and retest, Executive steering committee, Third‑party review

      What Schedule Slack Would Actually Keep You Sleep at Night?

      • How much schedule contingency (weeks or months) do you currently have between critical equipment handover and the installation window? Options: >6 months, 3–6 months, 1–3 months, <1 month
      • What minimum reliability or intervention risk do you require from equipment to accept compressed commissioning (e.g., allowable probability of intervention in first 5 years)? Options: <0.5% per year, 0.5–1% per year, 1–2% per year, Unspecified / qualitative
      • Are there hard contract dates that cannot be moved under any circumstance (e.g., drilling rig demobilization, insurance windows)? If so, list them.
      • What level of reporting cadence and transparency from suppliers makes you comfortable when schedule risk is elevated (daily standups, weekly RAG reports, milestone dashboards)? Options: Daily standups, Twice-weekly updates, Weekly RAG reports, Monthly milestones only, On-demand deep dives
      • Would you consider schedule‑risk mitigations that increase cost (e.g., overtime manufacturing, premium logistics)? If yes, under what conditions? Options: Yes — up to a defined cost cap, Yes — if critical to weather window, Maybe — case by case, No

      Documentation, Records and Traceability — The Paperwork That Keeps Things Moving

      • Which documents are mandatory before shipment for you to accept handover (ICDs, FAT reports, material certificates, serialization, test records)? Options: ICDs/interface drawings, FAT/HIL reports, Material certificates, Serialization/traceability, Maintenance manuals, Software release notes
      • How do you prefer document exchange and version control to be handled (shared repository, PLM access, email bundles, EDM with permissions)? Options: Shared PLM/EDM with access, Secure file share / repo, Email bundles with sign-off, Vendor portal
      • Are there specific supplier QA metrics or dashboards you require during manufacturing (weekly NCR counts, open nonconformances, test pass rate)? Options: NCR counts, Open NC aging, Test pass rate, Schedule vs planned weeks, Other
      • Who on your side will be responsible for reviewing and approving these documents and metrics, and what is their typical turnaround?
      • Do you require third‑party inspection or certification for specific items (forging sign-off, pressure vessel stamp, classification society approval)? Options: Yes — forging/pressure vessels, Yes — control/electrical systems, Yes — materials verification, No, Under discussion

      What Would Make You Feel Confident Enough to Move Forward?

      • If you had one simple deliverable from a supplier this week that would materially reduce your project anxiety, what would it be (revised integrated schedule, risk register, supplier capacity proof, sample FAT report)? Options: Revised integrated schedule, Detailed risk register, Supplier capacity & resource plan, Preliminary FAT report with results, List of long‑lead PO statuses
      • How important is supplier vertical integration (forging → machining → assembly) versus lowest cost when the calendar is the single binding constraint? Options: Vital — schedule control trumps cost, Important — balanced with cost, Neutral — cost prioritized, Unsure
      • What governance forum would you value to manage schedule and design changes (weekly steering committee, joint change board, commercial review meeting)? Options: Weekly steering committee, Joint engineering change board, Commercial review on milestones, Escalation matrix only
      • Are you open to a collaborative ‘what‑if’ re-sequencing exercise with manufacturing and SURF to preserve the installation window? Options: Yes — immediate workshop, Yes — within weeks, Maybe — need executive approval, No

      Concrete Next Steps — What We Need From You to De‑Risk Delivery

      • If we were to prepare a prioritized mitigation plan, which three items must it include to be useful to you?
      • Which stakeholder(s) must be involved in a rapid alignment workshop to make binding decisions (name roles: Project Director, VP Development, SURF lead, Procurement)?
      • What data package would you be willing to share to accelerate our assessment (current Gantt, POs, vendor lead‑time confirmations, FAT reports)? Options: Full Gantt / schedule, PO & supplier lead‑time confirmations, FAT/HIL reports, Interface control docs, All of the above
      • How soon can you commit to a 90‑minute alignment session to review critical path, long‑lead status, and interface gating items? Options: Within 48 hours, Within 1 week, Within 2 weeks, Later / unsure
      • Finally, what would success from this Current State Mapping look like for you in one sentence?
  2. Outcome Discovery

    Define measurable success signals (first‑oil date, 25‑year reliability at 15k PSI, allowable intervention risk) and hard constraints on schedule and budget.

    Discovery Questions

    Start Line: Your First‑Oil Target (Let’s Put a Date on the Map)

    • What is your target first‑oil date or the installation weather window? (enter date or range)
    • How critical is hitting that target on‑time for the project's overall sanction and investment metrics? Options: Mission‑critical — missing it is unacceptable, Very important — costly but potentially manageable, Important — some flexibility, Nice‑to‑have
    • If the first‑oil date slips, what are the top three concrete consequences you fear (financial, contractual, schedule knock‑on, reputational)?
    • Who in your organization has the final sign‑off authority for the first‑oil milestone and any associated trade‑offs? Options: Project Director, VP of Development, Investment Committee, Program Management Office (PMO), Operations Lead, Other
    • Have you suffered a subsea delivery delay on a prior project that materially affected first oil? Please describe briefly (what failed, impact, and root cause if known).

    The Reliability Bar You Can’t Lower

    • If each unplanned subsea intervention costs several million dollars and weeks of vessel time, how many interventions over 25 years would you tolerate before declaring the system unacceptable? Options: Zero interventions, 1 intervention in 25 years, 2–3 interventions in 25 years, More than 3 — please specify
    • Which formal reliability metric best maps to your acceptance criteria for the system? Options: 25‑year no‑intervention at 15k PSI, Mean Time Between Failures (MTBF) with target value, Probability of Failure on Demand (PFD), Annual failure rate (%), Other — describe
    • Which failure modes keep you awake at night for this project? (select all that apply) Options: Hydraulic/control system failure, Tree valve or sealing failure, Connector/stack fatigue, Manufacturing/forging defects, Corrosion or erosion, Interface failures with SURF contractor, Installation‑related damage, Other
    • What specific tests, evidence, or field experience would convince you the system meets your reliability bar? Options: Full system HIL/FAT witnessed, Pressure‑cycle endurance testing, Materials traceability and forging records, Field performance data from comparable installations, Third‑party certification, Accelerated life testing
    • What is your acceptable time‑to‑recover after an unplanned subsea failure (mobilization plus repair) before it becomes a project crisis? Options: <2 weeks, 2–4 weeks, 1–2 months, >2 months
    • How detailed should the reliability risk register be for you to feel comfortable (high‑level, moderate, or full deep‑dive with mitigations and owners)? Options: High‑level summary, Moderate with key failure modes and mitigations, Comprehensive with owners and quantitative risk

    The Budget‑Line That Stops Everything

    • If manufacturing costs or change‑orders pushed the subsea equipment budget up by 10–20%, would you still proceed — and under what conditions? Options: Yes, with contingency adjustments, Yes, if schedule remains intact, Conditional — would require scope reductions, No — hard budget cap reached
    • What is the hard budget cap for the subsea equipment scope (enter an absolute value or percent over FEED)?
    • Do you hold a separate contingency fund for manufacturing/supplier delays tied specifically to long‑lead items? Options: Yes — amount defined, Yes — amount TBD, No formal contingency
    • Which trade‑offs would you consider to protect the first‑oil date if costs rose (select all that apply)? Options: Reduce scope or non‑critical spares, Pay to accelerate manufacturing at premium, Defer non‑critical features to later change orders, Increase acceptance risk for certain tests, Seek owner‑funded mitigation at later stages
    • Who must approve any budget increase and what is the escalation path (list roles and thresholds)?
    • Do you plan to use contractual incentives or penalties tied to delivery milestones (select all that apply)? Options: Liquidated damages for late delivery, Incentives for early delivery, Performance bonds, Defined remediation plans instead of LDs, Insurance‑backed remedies

    The Non‑Negotiables — What We Must Not Touch

    • Which single constraint would you walk away from the project over — schedule, budget, performance/reliability, or regulatory compliance? Options: Schedule (first‑oil/install window), Budget hard cap, Performance/reliability target, Regulatory/compliance requirement, None — willing to renegotiate
    • Please select the hard technical constraints that cannot be changed for this project (select all that apply). Options: 15,000 PSI rating, Target water depth (meters) — please specify in next field, First‑oil or installation window, Host facility interface limits, Material specifications and certifications, Environmental/regulatory limits
    • Are there mandatory regulatory approvals, third‑party certifications, or JV signoffs that define acceptance and are non‑negotiable? Options: Yes — list required in the next field, No, Unsure / need to confirm
    • Which interface signoffs or host constraints must be complete before we can ship (select all that apply)? Options: SURF contractor connection sign‑off, Umbilical termination acceptance, FPU integration checklist sign‑off, Installation tooling and fit‑check complete, Environmental permits, Other
    • Who on your side is empowered to declare a 'stop‑ship' or an absolute non‑conformance that halts progress? Options: Project Director, Technical Authority / Lead Engineer, QA/QC Manager, Commissioning Lead, Operations Representative, Other

    If We Only Had One Metric

    • If you could present one measurable success signal to the investment committee, which single KPI would you choose? Options: First‑oil date certainty (on schedule), 25‑year reliability at pressure rating, On‑time delivery % for long‑lead items, System uptime after commissioning, Total cost vs budget
    • Please rank your top three measurable success signals and briefly explain why each matters to decision‑makers.
    • For each selected KPI, what specific tolerance or threshold do you require (give numeric values and units)?
    • Who will own reporting these KPIs internally and how often should stakeholders receive updates? Options: Project Director, VP of Development, PMO / Program Controls, Operations Lead, Joint Venture Reporting, Other
    • What documentation or evidence will satisfy each KPI (select all that apply)? Options: Test certificates and FAT/HIL reports, Manufacturing traceability and forging documentation, Third‑party verification or certification, Field trial/performance data, Acceptance sign‑off forms

    The Trade‑Off Conversation We Avoid — Let’s Have It Now

    • If forced to choose, would you prefer guaranteed schedule (with paid acceleration) or guaranteed design/reliability even if first oil is later? Options: Guarantee schedule with premium acceleration, Guarantee design/reliability and accept a later date, Hybrid — accelerate critical path only, Undecided — need guidance
    • Which areas are acceptable for scope reduction to preserve schedule if required (select all that apply)? Options: Non‑critical spares, Optional monitoring/analytics features, Secondary testing beyond baseline, Cosmetic/packaging items, Field‑upgradeable items
    • How would you like trade‑off options presented so you can pick quickly under pressure? Options: Ranked menu of options, Fully costed scenarios, Decision trees with quantified risk, Recommended single option with rationale
    • At what point of schedule slippage should we automatically escalate to executive sponsors? Options: 1 week slippage, 2–4 weeks, 1–2 months, Any slippage beyond contingency
    • What approvals and roles are required to implement a trade‑off (list roles and monetary/time thresholds)?

    What Success Feels Like — The Human Side

    • When first oil flows and the team celebrates, what relief, pride, or proof will tell you the project was worth it?
    • Which stakeholders' satisfaction is most critical to your career and to project continuity (select up to three)? Options: Investment Committee, Operations / Opex team, Drilling/Field team, Regulators, JV Partners, Board / Executive
    • What delivery experience elements would reduce your stress during manufacturing and installation (select all that apply)? Options: Transparent weekly milestone dashboard, Proactive risk alerts with proposed remedies, Dedicated single point of contact, On‑site engineering support during critical phases, Clear pass/fail acceptance criteria and visibility
    • What are your biggest fears around vendor interfaces during SURF and FPU integration (describe a specific scenario if possible)?
    • If we could remove one major worry from your plate before commissioning, what would it be and why?

    The 'How We'll Measure It' Playbook

    • If a board member demands proof that reliability will meet the 25‑year target, what three pieces of evidence would satisfy them?
    • Which monitoring and reporting tools do you want during manufacturing and testing (select all that apply)? Options: Live manufacturing dashboard, Weekly risk register updates, HIL/FAT video evidence, Material traceability portal, Third‑party test reports, Inspection/photo logs
    • What cadence and format do you prefer for formal milestone gate reviews? Options: Weekly written status + monthly gate review, Biweekly status calls + milestone dashboard, Monthly executive steering committee, On‑demand if trigger thresholds met
    • How should acceptance testing be structured so results are unambiguous? Options: Pass/fail criteria by test, Third‑party witness or certification, Pre‑defined retest limits and windows, Clear remedial actions with deadlines, Signed acceptance forms
    • What level of access to engineering and manufacturing records during build do you require? Options: Full live access to records, Limited periodic reports and summaries, Access on request, Access under NDA / controlled portal

    If the Worst Happens — Your Recovery Playbook

    • If a critical long‑lead component misses the installation window, what recovery approach would you prefer? Options: Mobilize alternate vendor at premium, Reschedule installation, Shift scope to available systems and defer others, Implement temporary bridging solutions
    • Which contractual remedies do you require to manage delivery risk (select all that apply)? Options: Liquidated damages for delays, Performance bonds, Incentives for early delivery, Defined remediation and repair plans, Insurance‑based recovery
    • What maximum exposure (time and cost) would you accept before you ask for vendor replacement or major contract renegotiation? Options: <2 months / <$5M, 2–6 months / $5–20M, >6 months / >$20M, Depends on cause and remedy
    • Who are the emergency decision‑makers (names/roles) empowered to decide recovery vs termination?
    • What contingency spares, pre‑staged resources, or logistics support do you expect the supplier to hold or commit to? Options: Critical spare valves, Connector assemblies, Control electronics spares, Subsea tooling packages, No spares expected from supplier, Other
  3. Solution Experience

    Walk through how the proposed subsea architecture and our vertically integrated manufacturing schedule meet the customer’s timeline and reliability needs using their real scenarios.

    Experience Meetings

    • Experience Prep & Current-State Confirmation
    • Scenario-Based Solution Walkthrough
    • Manufacturing Proof & Vertical-Integration Walkthrough
    • Integration, SURF & Installation Sequencing Session
    • Validation, Sign-off Criteria & Next Steps
    • Establish contingency triggers, associated mitigations, and commercial remedies to reduce customer risk exposure.
    • Agree next decision points and any clarifications needed for detailed schedule alignment.
    • Supplier to deliver a scenario-overlay schedule (Gantt) with milestone ownership and critical-path callouts within 48 hours.
    • Customer to confirm which internal approvals align to the supplier milestones and provide expected approval lead times.
    • Jointly nominate a single point of contact for rapid decisions on spec clarifications and schedule slippages.
    • Manufacturing control overview
    • Prove that vertical integration materially shortens and de-risks the critical manufacturing path.
    • Demonstrate through data that our delivery performance supports the customer's first-oil timeline.
    • Confirm that the reliability assurance package meets the customer's 25-year / 15k PSI requirement or identify gaps to close.
    • Supplier to provide redacted project KPI pack (on-time delivery, NCR rates, FAT summaries) for two comparable projects.
    • Customer to list any additional manufacturing evidence required for their internal technical gate review.
    • Agree a joint review point for long-lead procurement status every 4 weeks until shipment.
    • Interface map review
    • Align supplier delivery milestones with SURF and vessel installation sequencing to protect the weather window.
    • Agree concrete acceptance criteria and gating events required prior to loadout and installation.
    • Pre-work review
    • Produce an integrated interface Gantt with acceptance gates and contingency triggers for customer review within 72 hours.
    • Customer and SURF contractor to confirm interface owners and contact details for execution week communications.
    • Define and document remediation steps and associated commercial remedies for specific delay thresholds.
    • Summary of proofs vs future-state
    • Obtain customer confirmation that the Solution Experience proves the agreed future-state or capture precise objections.
    • Agree acceptance criteria and sign-off authorities required to move to Solution Scope and Mutual Commit.
    • Create a clear action register with owners and deadlines to resolve outstanding gaps.
    • Customer to provide formal confirmation (email or signed note) that the future-state is accepted or list remaining objections within 5 business days.
    • Supplier to draft a Solution Scope stub (equipment list, acceptance criteria, key milestones) for mutual review within 7 business days.
    • Establish weekly governance cadence (owner, time, attendees) to track action-item closure until contract signature.
    • Lock a clear, one-sentence current state that the solution will address.
    • Agree a quantified statement of consequence if timelines or reliability targets are not met.
    • Define a single, measurable future-state outcome the experience must prove.
    • Confirm pre-work completeness and responsible parties for outstanding inputs.
    • Customer to deliver final consolidated project schedule (drill, vessel, installation windows) and long-lead list within 3 business days.
    • Supplier to provide template for consequence quantification (cost per month, vessel rate assumptions) for customer to validate.
    • Assign owner to the one-sentence current-state and future-state wording for use in all subsequent meetings.
    • Recap of current-state & future-state
    • Prove that the proposed architecture and manufacturing timeline deliver the agreed future-state for both customer scenarios.
    • Surface and confirm gating milestones and contingency triggers tied to customer consequences.
    • Obtain real-time validation from the customer at key steps to avoid assumptions.
    • Current-state one-sentence
    • Open gaps & risk register
    • Delivery vs vessel campaign overlay
    • Historic performance evidence
    • Select and confirm scenarios
    • Critical-path & long-lead management
    • Architecture mapping to scenario 1
    • Acceptance & sign-off criteria
    • Acceptance & commissioning gates
    • Consequence quantification
    • Governance for changes
    • Define future-state one-sentence
    • Reliability assurance (design & test)
    • Manufacturing timeline overlay (scenario 1)
    • Contingency triggers & remedies
    • Traceability and change-control
    • Consequence check
    • Agreed next steps and owners
    • Validation gates & rules for the experience
    • Integration responsibilities & escalation path
    • Next steps & assignments
    • Customer Q&A and validation points
    • Repeat mapping for scenario 2 (risk case)
  4. Solution Scope

    Specify equipment, interfaces, testing scope, acceptance criteria, and responsibilities across supplier, SURF contractor, and host facility.

    Scope Configuration

    • Manufacture and Deliver Subsea Trees
    • Manufacture and Deliver Subsea Manifolds
    • Assemble and Test Subsea Control Modules
    • Manufacture and Deliver Electro‑Hydraulic Umbilicals
    • Fabricate and Deliver Flowlines and Riser Sections
    • Supply Wet‑Mate Connectors and Connection Hardware
    • Perform Factory Acceptance Testing and System Integration
    • Perform Hydrostatic and 15,000‑psi Pressure Testing
    • Deliver NDT Reports and Material Certification Package
    • Provide Offshore Installation Supervision and ROV Support
    • Conduct Pre‑Commissioning Functional and Leak Tests
    • Supply Long‑Term Spares and Critical Spare Kits

    Scope Questions

    Manufacture and Deliver Subsea Trees

    • How many subsea trees are required for the baseline scope? Options: 1-5, 6-20, 21-50, 51+
    • Which tree architecture(s) do you require? Options: Vertical (VXT), Horizontal (HXT), Multi-bore / Matrix, Custom / Vendor-specific
    • What pressure and temperature ratings must each tree meet? Options: <=10,000 psi, 10,000-15,000 psi, 15,000 psi (specify temp), Other (specify)
    • What is the target delivery milestone for first units relative to the installation window? (e.g., date or weeks before mobilization)
    • Are there specific interface standards or connection types required between tree and manifold/flowline? Options: API-standard, Proprietary client spec, Vendor-provided mating flange, Other (specify)
    • Which acceptance activities are required at factory before shipment (select all that apply)? Options: FAT (functional), Hydrostatic pressure test, HIL / system simulation, NDT and material traceability review, Witnessed assembly
    • Do you require integrated tooling or special lifting / shipping frames supplied with each tree? Options: Yes - provide spec, No, Maybe - discuss options

    Manufacture and Deliver Subsea Manifolds

    • How many manifold assemblies are needed and are there phased deliveries? Options: Single manifold, Multiple manifolds - same spec, Multiple manifolds - varying specs, Phased delivery required
    • What production and piping configurations must the manifold support (e.g., number of templates, tie-ins, pigging, pig launchers)?
    • What operating pressures and design life must the manifold accommodate? Options: Up to 10,000 psi, Up to 15,000 psi, Greater than 15,000 psi, Specify other
    • Are there integration/interface drawings or SURF contractor specs we must adopt? Options: Yes - provide drawing pack, Partially - provide key interfaces, No - vendor to propose
    • Which testing and inspection levels are required for manifolds prior to delivery? Options: Full FAT + system HIL, Hydrostatic test only, FAT + NDT + traceability, Client witness required
    • Do you require manifold skid-mounted systems, subsea templates, or both? Options: Skid-mounted, Template / subsea foundation, Both, Unsure - discuss
    • Are embedded sensors or instrumentation to be supplied by vendor or client? Options: Vendor supplied & integrated, Client supplied & vendor to install, Client to install offshore

    Assemble and Test Subsea Control Modules

    • How many control modules (SCM/UMD) are in scope and what are the deployment locations? Options: 1-3, 4-10, 11-30, 30+
    • What control architecture is required (electro-hydraulic, all-electric, hybrid)? Options: Electro-hydraulic, All-electric, Hybrid, Client-specified
    • Do modules need to integrate with existing host facility control systems (DCS/SCADA)? If yes, provide interface requirements. Options: Yes - provide protocol/spec, No - standalone, Partial integration
    • What level of bench testing is required before shipment (power-on tests, comms, functional scenarios)? Options: Full FAT with scenario scripts, Basic acceptance tests, HIL required with simulator
    • Are client or third-party control software licenses required or provided? Options: Vendor provides, Client provides, Open-source / standard
    • Do you require redundant control channels or failover architectures? Options: Full redundancy, Partial redundancy, No redundancy required
    • List any environmental or packaging constraints for control modules (temperature range, EMI shielding, shock/vibration limits).

    Manufacture and Deliver Electro‑Hydraulic Umbilicals

    • What is the total umbilical length and number of individual umbilicals required? Options: Single short (<2 km), Single long (>2 km), Multiple umbilicals, Specify lengths
    • Which circuits are required in the umbilical (electrical, fiber-optic, hydraulic, chemical injection)? Options: Power (electric), Fiber optic, Hydraulic (pressure-rated), Chemical injection, All of the above
    • Are there specific armor, bend radius, or burial requirements for the umbilical? Options: Armored, Unarmored, Burial required, Controlled bend radius spec
    • What are the required termination types at each end (wet-mate, dry-mate, specific connector types)? Options: Wet-mate, Dry-mate, Hybrid, Custom - provide spec
    • What delivery schedule and splicing/testing milestones (e.g., laydown, pre-lay trials) do you require?
    • Do you require FAT and HIL of umbilical termination assemblies prior to shipment? Options: Yes - vendor to perform, Yes - with client witness, No - test offshore
    • Are onshore storage, preservation, and pre-load testing services required before transportation? Options: Yes, No, Maybe - discuss

    Fabricate and Deliver Flowlines and Riser Sections

    • Which flowline materials and specifications are required (e.g., carbon steel, CRA, internal coatings)? Options: Carbon steel, Corrosion resistant alloy (CRA), Internally coated, Specify in free text
    • What are the required diameters, wall thicknesses, and pressure ratings for each segment?
    • Are pipelay method constraints (S-lay, J-lay, Reel-lay) relevant to fabrication or pre-assembly? Options: S-lay, J-lay, Reel-lay, Pipe-in-pipe, Not specified
    • Do you require factory-assembled spool pieces or full-length prefabricated runs? Options: Spool pieces only, Prefabricated long runs, Both, Client preference
    • What QA/QC and NDT coverage (RT, UT, MPI, DPI) is required for flowlines and riser sections? Options: RT/UT required, MPI/DPI required, Full NDT package, Client to define
    • Are installation aids (lifting lugs, handling frames, buoyancy modules) to be supplied with the piping deliverable? Options: Yes - vendor to supply, No - client supplies, Specify requirements
    • Do you require pre-installation hydrotesting or internal cleaning & preservation prior to shipment? Options: Hydrotest required, Cleaning & preservation required, Both, No

    Supply Wet‑Mate Connectors and Connection Hardware

    • What types and quantities of wet-mate connectors are required (power, fiber, hydraulic)?
    • Are connectors standard catalog items or do they require custom pinouts / pressure ratings? Options: Standard catalog, Custom pinout, Custom pressure rating, Other
    • Is client witness of connector assembly and pressure testing required? Options: Yes - at vendor facility, Yes - at third-party lab, No
    • Do connectors require subsea mate/demate tools, recovery tooling, or ROV interface designs? Options: Yes - supply tooling, No, ROV interfaces only
    • What acceptance criteria apply to connection hardware (electrical continuity, insulation resistance, hydraulic leak rate)?
    • Should dry-storage, preservation, and packing for long transits be included with connectors? Options: Yes - include preservation, No - client to handle, Discuss options
    • Are spares of connectors and critical pins required in the spares package? Specify desired coverage (e.g., 1 spare per 5 units).

    Perform Factory Acceptance Testing and System Integration

    • Which assemblies require FAT (trees, manifolds, control modules, umbilicals)? Options: Trees, Manifolds, Control modules, Umbilicals, All of the above
    • Will FAT be witnessed by client or third-party inspector, and at which vendor facilities? Options: Client witness, Third-party witness, No witness, Remote witnessing required
    • Do you require integrated system HIL testing that simulates host facility and SURF interfaces? Options: Full HIL with host simulation, Partial HIL, No HIL required
    • What functional test scenarios must be executed and passed during FAT (e.g., emergency shut-in, choke modulation)?
    • Are cyber/communication protocol validations (MODBUS, OPC, custom) required as part of FAT? Options: Yes - list protocols, No, Limited protocol validation
    • What documentation must accompany FAT deliverables (test protocols, result logs, traceability matrix)? Options: Full test protocol & results, Summary report only, Traceability & certificates included
    • Do you require FAT failure modes & corrective action tracking for any remediation before shipment? Options: Yes - formal CARs required, No - informal fixes, Critical issues only

    Perform Hydrostatic and 15,000‑psi Pressure Testing

    • Which components require hydrostatic and high-pressure (up to 15,000 psi) testing? Options: Trees, Manifolds, Flowlines, Riser sections, Connectors
    • Do tests need to be witnessed or certified by a third-party inspector or classification society? Options: Yes - third-party witness, Yes - class society stamp, No witness required
    • What test durations, acceptance criteria, and allowable leakage rates are acceptable?
    • Are test media constraints applicable (sea water, fresh water, glycol, oil)? Options: Fresh water, Sea water, Glycol/water mix, Hydraulic oil
    • Do you require post-test non-destructive examination or dimensional checks after pressure testing? Options: Yes - NDT after test, No - only pre-test checks, Selective NDT
    • Should pressure testing include endurance / cyclic testing to demonstrate long-term reliability? Options: Yes - cyclic testing required, No - static only, Discuss required cycles
    • Are witnessed certification reports and pressure test curves required in the delivery package? Options: Full curves & certificates, Pass/fail summary only, Client-specific format

    Deliver NDT Reports and Material Certification Package

    • Which NDT methods are mandatory for your project (RT, UT, MPI, DPI, PMI)? Options: RT, UT, MPI, DPI, PMI, Other
    • Do you require mill test certificates (MTCs) and full material traceability for all pressure-containing parts? Options: Yes - full traceability, Partial traceability, Standard MTC only
    • Should NDT reports be delivered in a digital certified format and integrated into an electronic QA/QC folder? Options: Yes - electronic folder, PDF reports only, Paper reports acceptable
    • Is third-party NDT witness or certification by a recognized body required? Options: Yes - third-party witness, Yes - accredited lab, No
  5. Mutual Commit

    Finalize commercial terms, milestone schedule, risk allocation (including remedies for delivery delays), and governance for schedule and design changes.

    Agreement Modules

    • Statement of Work (SOW)
    • Master Supply Agreement (MSA)
    • Commercial Terms & Payment Schedule
    • Milestone Schedule & Installation Gantt
    • Risk Allocation & Remedies
    • Acceptance Testing & FAT/HIL Protocols
    • Change Control & Design Governance
    • Performance Guarantees & Warranty
    • Performance Security (Bond / Letter of Credit)
    • Insurance & Indemnities
    • Interface Responsibility Matrix & Integration Agreement
    • Logistics, Export/Import & Customs Plan
    • Spares, Obsolescence & Long‑Term Support
    • Final Acceptance & Handover Certificate
    • Termination & Dispute Resolution
    • Regulatory Compliance & Certification Package
  6. Deployment

    Operationalize rollout with readiness checks, enablement, and outcome validation.

    1. Pre-Deployment Readiness

      Confirm manufacturing critical path, long‑lead procurements, FAT/HIL readiness, and interface signoffs needed before shipment to meet the installation window.

      Readiness Questions

      Quick Pulse: Your Project in One Sentence

      • In one short sentence, what single outcome must this subsea procurement deliver for your sanction to be judged a success?
      • How far is your target first‑oil date from today? Options: < 12 months, 12–18 months, 18–24 months, 24–36 months, 36+ months
      • Where does your installation campaign’s primary weather window fall relative to that first‑oil target? Options: Firmly inside the campaign window, Tightly coupled to the window (low slack), Split across two seasons, Outside the preferred window (high risk), Unknown / still being defined
      • Who are the three core decision‑makers we should be talking to on schedule, technical acceptance, and commercial risk (name and role)?
      • How would you rate your team’s current confidence that the subsea equipment vendor will meet the delivery date that aligns with the installation campaign? Options: Very confident, Somewhat confident, Low confidence, Not confident at all

      If the Delivery Slipped a Year, What Keeps You Up at Night?

      • If manufacturing slipped twelve months, what single cascading impact would you fear most for the project (cost, regulatory, reservoir, partner support, other)?
      • Estimate the incremental cost impact of a one‑year slip on the project. Options: <$50M, $50–150M, $150–300M, $300–500M, >$500M / unknown
      • What portion of the overall schedule is rigid because it must align with a vessel/weather window (answer as a percentage and explain what’s inflexible)?
      • Have you experienced a weather‑window driven delay on a previous project? If yes, briefly describe the consequence and how you recovered. Options: Yes — major impact, Yes — moderate impact, Yes — minor impact, No
      • Who, in your organization, would be most affected politically or financially if the installation missed the weather window?

      Are You Betting on Manufacturers to Carry the Schedule?

      • Do you feel your incumbent or preferred manufacture path is actually holding the schedule, or are they buying time with optimistic forecasts?
      • Which vendor performance KPIs do you require to trust a manufacturing schedule? Options: On‑time delivery of milestones, On‑budget delivery, Yield / defect rates, Supplier lead‑time adherence, Testing pass rates, Other
      • Which manufacturing milestones should trigger escalation calls (choose all that apply)? Options: Forging completion, Machining complete, Assembly start, FAT scheduled, HIL scheduled, Shipment readiness
      • How frequently would you like formal, auditable progress reviews from the manufacturer? Options: Weekly, Bi‑weekly, Monthly, Milestone‑based only, Ad‑hoc on request
      • What contractual remedies or incentives have you found effective for keeping manufacturers accountable (brief examples welcome)?

      Where Do Interfaces Tend to Break—and Why?

      • Which interface in your execution plan do you quietly worry will derail installation if not perfectly aligned?
      • Please identify the primary technical integration points you expect us to own or coordinate (select all that apply). Options: Tree‑to‑umbilical control, Manifold‑to‑flowline connection, Control system to FPU integration, Umbilical termination and hang‑off, Assembly lift and loadout interfaces, Testing & commissioning data handover
      • Who currently owns final interface sign‑off for each critical interface you listed (operator, SURF contractor, vendor, host FPU)? Options: Operator, SURF contractor, Vendor, Host FPU/owner, Joint sign‑off/other
      • How mature are your interface documents (PIMs, ITPs, joint checklists) today? Options: Final and mutually signed, Draft under review, High‑level only, Not yet started
      • Tell us about one interface dispute you’ve seen and what ultimately caused the delay — e.g., unclear ownership, late data, or test failures.

      What Would 'On‑time, Low‑risk Delivery' Really Look Like?

      • If you could write the acceptance criteria for an ‘on‑time, low‑risk delivery’ in one sentence, what would it say?
      • Which of these success signals are non‑negotiable for you? Options: First‑oil date met, 25‑year reliability at 15k PSI proven, FAT + HIL passed with operator witness, All critical interface signoffs before shipment, Delivery within installation window
      • What is your maximum acceptable probability of requiring an intervention vessel in the first five years (choose range)? Options: <0.5%, 0.5–1%, 1–2%, 2–5%, >5% / unsure
      • How many weeks of schedule slippage (from vendor delivery) can you tolerate before the project becomes commercially at risk? Options: 0–4 weeks, 5–8 weeks, 9–16 weeks, 17–26 weeks, >26 weeks
      • Which acceptance tests or performance metrics must be demonstrated before you approve shipment (list and rank if possible)?

      How Much Design Change Is Too Much Once Manufacturing Starts?

      • At what point after manufacturing begins would even a small design change become unacceptable to you? Options: Before raw material procurement, After forging starts, After assembly begins, After FAT is complete, Never acceptable
      • Historically, how often have design changes been introduced after manufacture started on similar projects? Options: Never, Rarely (once), Occasionally (2–3 times), Frequently (4+ times)
      • Who in your approval chain is empowered to sign an urgent design change that affects schedule, and what is their typical lead time for a decision?
      • What financial allocation or contingency level are you willing to accept for late design changes? Options: None — vendor absorbs, Small fixed contingency, Shared cost model, Operator absorbs
      • If rework is required, what is the maximum additional calendar time you would accept per affected unit before you consider alternate routes (repair, replacement, redesign)? Options: <4 weeks, 4–8 weeks, 8–16 weeks, >16 weeks

      What Would Make You Trust Our Reliability Claims?

      • Would a vendor’s claim of 25‑year reliability at 15k PSI feel credible without field reference installations and detailed test evidence? Options: Yes — if independent test data provided, Maybe — depends on test depth, No — need field references
      • Which proof points would most convince you (select up to three)? Options: Field installations with similar specs, Full FAT/HIL data packages, Third‑party certification, Accelerated life testing, OEM material traceability and metallurgy records
      • How many comparable installations (depth/pressure/chemistry) do you expect as a minimum before you feel comfortable? Options: None required, 1–5, 6–20, 20+
      • Would you require operator‑witnessed FAT/HIL events, and if so, which ones absolutely must be witnessed? Options: Full system FAT, Critical closure system HIL, Control system integration tests, Witnessing optional — data review acceptable
      • What warranty or post‑installation support terms would meaningfully de‑risk the perceived reliability gap for you?

      If We Could Remove One Manufacturing Uncertainty, Which Would You Choose?

      • If you could eliminate a single manufacturing risk tomorrow, which would free the most schedule pressure—long‑lead procurement, assembly bottlenecks, testing capacity, or QA/inspection delays? Options: Long‑lead procurement, Assembly bottlenecks, Testing capacity constraints, QA/inspection delays, Other
      • Please list the long‑lead items you consider critical and their current lead times.
      • Are alternative or dual‑source suppliers prequalified for any of those long‑lead items? Options: Yes — fully prequalified, Partially prequalified, No — single source, Unknown
      • Would you accept staged or modular shipments (e.g., send test‑ready modules earlier) to de‑risk the installation schedule? Options: Yes — actively prefer, Maybe — depends on cost and interfaces, No — prefer single integrated shipment
      • How would you like progress on these critical items communicated (dashboard cadence and minimum metrics)? Options: Weekly dashboard with Gantt & % complete, Bi‑weekly written report, Monthly executive summary, Real‑time access to vendor schedule

      Who Holds the Button on Installation Day?

      • If an unexpected issue appears during loadout or SURF hookup, who is authorized to stop or alter the operation and what criteria must they cite?
      • Do you have a joint governance and escalation plan for installation execution today? Options: Yes — formal with RACI, Drafts exist, No — ad‑hoc arrangements, Unknown
      • Which contingency triggers should auto‑pause the operation (select all that apply)? Options: Weather exceedance threshold, Failure of critical test, Interface misalignment found, Unplanned equipment damage, Regulatory hold
      • What documentation and interface signoffs must be completed and verified before shipment leaves the yard? Options: Final ITPs, Operator witness FAT/HIL certificates, Signed interface checklists, Loadout engineering drawings, All of the above
      • What level of vendor onsite support do you expect during loadout and first‑lift installation (team size, roles, duration)?

      What Would It Take to Move to Mutual Commit?

      • What single commercial or governance change would persuade you to mutually commit within 30 days (e.g., revised milestone, performance bond, staged liability, increased witness rights)?
      • Which commercial terms are absolute deal‑stoppers if not present? Options: Liquidated damages for late delivery, Performance bond, Long‑term warranty, Acceptance criteria tied to payment, None — flexible
      • What risk allocation for delivery delays do you find acceptable? Options: Vendor bears most risk, Shared risk with clear triggers, Operator bears most risk, Case‑by‑case negotiation
      • What governance cadence would you want after mutual commit (steering committee frequency, technical working groups, vendor PMO touchpoints)? Options: Weekly program meeting + monthly steering, Bi‑weekly technical + monthly exec, Monthly only, As required / milestone driven
      • Who on your side must sign the mutual‑commit and what is their realistic decision timeline?
    2. Deployment Enablement

      Coordinate delivery, loadout, SURF integration, and installation sequencing with owners, Gantt milestones, and contingency triggers.

    3. Validation Checklist

      Execute commissioning and acceptance tests, document performance vs acceptance criteria, and verify post‑installation reliability checks are complete.

      Validation Questions

      How this project landed on your desk

      • Tell us briefly: what is the sanctioned project name, your role, and the single biggest outcome you’re accountable for?
      • When was the investment committee sanction and what is the target first‑oil month (or installation campaign window)?
      • Where are you in vendor selection / contracting today? Options: FEED only, Shortlisting vendors, Negotiating supply contract, Contract signed, manufacturing planning, Other
      • Who on your team will be the day‑to‑day contact for subsea equipment delivery and integration?
      • If you had to name one project metric that feels most at risk today, what is it (e.g., first‑oil date, installation window adherence, capital cost, production ramp)? Options: First‑oil date, Installation window adherence, CapEx, Production ramp, Operational uptime / reliability, Other

      Who’s actually holding the watch?

      • If your team had to bet on where the real decision friction will show up, what unexpected stakeholder will most likely slow approvals or change scope?
      • List the approval owners and influencers for design, schedule, procurement, and budget (names, roles, and their absolute deadline constraints).
      • How aligned are the following groups on schedule and risk appetite? Options: Fully aligned, Mostly aligned with minor differences, Significant misalignment on schedule, Significant misalignment on risk, Unknown / unclear
      • Which single stakeholder’s sign‑off has historically caused the largest schedule slips in your projects? Options: Operator technical authority, Procurement/PCO, Finance/Investment, SURF contractor lead, Host facility owner, Other
      • How does each key stakeholder define “on‑time, low‑risk delivery” in measurable terms?
      • Who is empowered to approve schedule or design changes after contract award, and what escalation path do you expect for disputes?

      Where projects like this usually fail — tell me your story

      • When you look back at comparable subsea projects, what single failure mode would you say caused the largest cost/time impact? Options: Manufacturing delay on long‑lead, Integration mismatch with SURF/FPU, Late design changes, Poor vendor quality control, Logistics/loadout delays, Other
      • Which long‑lead components keep you awake at night (select all that apply)? Options: Forgings / machined bodies, Control system electronics, Umbilical cores, High‑pressure valves, Specialty coatings / materials, Other
      • Give a concrete example of a vendor performance issue you’ve faced (what happened, timeline impact, how it was resolved).
      • Where do your integration points with SURF and the host FPU create the most uncertainty (mechanical interfaces, control logic, schedule handoffs, testing)? Options: Mechanical interfaces, Control & communications, Schedule handoffs, Testing & acceptance, All of the above, Other
      • Describe a near‑miss or close call on a past project—what early signals were missed and what would you want to capture earlier next time?
      • How do previous supplier warranties, workmanship records, or reference projects influence your current vendor risk tolerance?

      If time slips, how bad does it get?

      • If the subsea equipment delivery shifts beyond your weather‑window by one month, does that delay mean a few extra days or a full year of cost and schedule escalation? Options: A few days / manageable, Several weeks with cost pressure, Likely a full campaign slip (~12 months), Unsure
      • What is your absolute last acceptable installation season (month/year) before first‑oil is compromised?
      • How do you currently quantify the cost of a slipped installation campaign (vessel day‑rate exposure, deferred production loss, contractual penalties)? Options: Vessel day‑rate & mobilization, Deferred production revenue, Contractual liquidated damages, Rework & re‑mobilization costs, Combination of the above
      • What contingency triggers do you want explicitly defined (e.g., X‑week manufacturing delay triggers alternative procurement or chartering of a standby vessel)?
      • Have you modelled compressed commissioning (shortened FAT, parallel testing) as an acceptable mitigation—what margin of schedule compression is tolerable? Options: None, 1–2 weeks, 2–4 weeks, 4+ weeks, Unsure

      What would 25 years of trouble‑free production actually look like to you?

      • What specific reliability metrics matter most: MTTF, probability of intervention over 25 years, allowable leak rate, or something else? Options: MTTF / MTBR, Intervention probability, Leak / emission limits, Pressure hold / integrity metrics, Other
      • How do you define an acceptable intervention risk (e.g., 1 intervention per 25 years, per system, per cluster)? Options: No more than 1 intervention in 25 years, 1–2 interventions in 25 years, As low as reasonably practicable, Undetermined / need to define
      • Which success signals will you use to sign off the subsea system at commissioning (first‑oil achieved, performance vs acceptance curves, demonstrable reliability tests)? Options: First‑oil on scheduled date, Performance vs acceptance criteria, Successful HIL / FAT results, Zero critical defects at installation, Other
      • What hard constraints on capex or schedule are non‑negotiable, and where are you willing to trade cost for schedule or vice versa?
      • How emotionally costly would an unplanned intervention be for your team—what reputational or career exposure do you consider?

      Do you trust the maker to own the timeline?

      • When a vendor promises vertical integration will guarantee schedule, what would make you skeptical rather than reassured?
      • Rate your current confidence in supplier manufacturing delivery on comparable projects. Options: Very high, Moderately high, Neutral, Moderately low, Very low
      • Which manufacturing milestones are on your critical path and must be visible weekly (e.g., forging completion, machining start, assembly start, HIL test window)? Options: Forging completion, Machining start, Assembly start, System integration, HIL/FAT window, Other
      • What evidence would you need to prove the supplier’s manufacturing control—sample KPIs, factory tour, third‑party audit, or test data? Options: Factory tour / witness, KPI dashboard, Third‑party audit, Detailed test reports, Reference project visit, Other
      • Are there supply‑chain single points of failure you’re most worried about (specialty vendors, single source forgings, proprietary electronics)? Please list and indicate lead times.

      What would make you pause before we loaded out?

      • What minimum set of tests and signoffs do you require before authorizing shipment to the installation site? Options: Complete FAT & HIL passed, Mechanical interface signoffs, Documentation & spares verified, Quality certificates and NDE reports, All of the above, Other
      • Who has authority to sign final acceptance for shipment and what documentation do they require?
      • How do you prefer acceptance evidence to be presented—detailed test logs, executive summary with KPIs, video of critical tests, or live witness? Options: Detailed test logs, Executive KPI summary, Video evidence, Live witness (onsite/remote), Combination
      • Which interface signoffs from SURF and FPU must be in place before loadout? Options: Mechanical mating drawings, Control system comms test, Installation method statement, Loadout and transport certificates, All of the above
      • What spare parts and critical consumables do you insist are shipped with the first delivery, and who inventories them on receipt?

      If the schedule breaks, who does what and when?

      • What remedies do you expect for supplier‑caused delivery delays (liquidated damages, accelerated deliveries, replacement equipment, performance bonds)? Options: Liquidated damages, Accelerated production at supplier expense, Replacement units, Performance bonds/guarantees, Other
      • Describe your preferred governance cadence for resolving schedule or design changes (weekly program reviews, executive steering, joint change board). Options: Weekly program review, Biweekly technical working group, Executive steering committee, Joint change control board, Other
      • Who are the named escalation contacts (operator, supplier, SURF contractor) you want on a critical‑path call within 24 hours of a trigger?
      • What contractual mechanisms have you used before that actually worked to speed recovery—what would you want to keep or avoid?
      • How do you expect post‑installation support to be structured (on‑call OEM teams, spares pool, guaranteed MTTR targets)? Options: On‑call OEM team, Dedicated on‑site support, Spares pool managed by operator, Guaranteed MTTR targets in contract, Other

      If you could lock three non‑negotiables into the contract, what would they be?

      • Please list and rank up to five non‑negotiable items (e.g., absolute delivery month, defined intervention risk, acceptance criteria, penalty structure).
      • Which of these are tradeable if we offered more schedule certainty, and which are absolute red lines?
      • How often would you like a shared program dashboard updated and who needs access (project team, exec sponsor, SURF contractor)? Options: Daily (critical phases), Weekly, Biweekly, Monthly, On key milestones only
      • Would a dedicated shared channel for issues and continuous improvement (e.g., joint Slack/Teams channel) help your governance and fast decision making? Options: Yes, Maybe, No
      • Realistically, how soon should we schedule a joint workshop to translate these non‑negotiables into practical milestones and acceptance tests? Options: Within 1 week, 1–2 weeks, Within a month, Longer / TBD
  7. Success

    Review outcomes against success signals, capture lessons learned, and maintain a shared channel for issues and continuous improvements.

    Success Reviews

    • Success Signal Review Workshop
    • Lessons Learned Retrospective
    • Reliability & Continuous Improvement Review
    • Issue Triage, Shared Channel & Governance Kickoff
    • Executive Success Review & Formal Sign‑off

    Issues & Enhancements

    • Populate and triage the issue register in the new channel, assigning owners and SLAs.
    • Establish monitoring, alerting, and analytics approach to detect degradation early.
    • Create a prioritized CI backlog tied to reliability improvements with owners.
    • Agree on KPI definitions and a reporting cadence for reliability performance.
    • Deliver a Reliability Action Plan covering residual risks, mitigations, spares list, and intervention thresholds.
    • Set up KPI dashboard and schedule recurring reliability reports to stakeholders.
    • Procure or reserve critical spares and confirm logistics lead times.
    • Create CI backlog tickets with acceptance criteria and owners for each improvement item.
    • Current Open Issue Register Review
    • Launch a governed shared channel for live issue tracking with agreed access and naming conventions.
    • Agree triage rules, SLAs, and escalation paths for open issues and new defects.
    • Assign owners for existing open issues and schedule recurring triage sessions.
    • Commit to a reporting cadence and digest format for executive and operational audiences.
    • Create the shared channel and invite predefined stakeholder list; publish governance charter.
    • Welcome & Objectives
    • Configure weekly automated digest and KPI reports for distribution.
    • Deliver short onboarding session and a quick reference guide for channel users.
    • Executive Summary & Decision Request
    • Achieve executive sign‑off on project success or documented exceptions with remediation commitments.
    • Agree commercial reconciliations or remedies tied to unmet success signals as appropriate.
    • Confirm ongoing governance cadence and knowledge transfer plan.
    • Authorize publication of lessons and release of agreed deliverables to broader stakeholder groups.
    • Circulate executive minutes and sign‑off document with signatures and condition list.
    • Finalize commercial adjustment or remedy paperwork and route for approval.
    • Publish approved lessons learned to the customer portal and internal knowledge base.
    • Schedule the first quarterly governance review and hand over ongoing CI responsibilities.
    • Confirm which success signals are met, partially met, or unmet.
    • Quantify the project impact (days, $M, intervention risk) for each identified gap.
    • Agree on remedial path or formal acceptance with named owners and deadlines.
    • Produce a short 'Success Decision' artifact for exec sign‑off.
    • Publish consolidated Success Signals vs Outcomes report and circulate to all stakeholders.
    • Assign remediation owners for each unmet signal with target dates and resource needs.
    • If acceptance granted with deviations, document acceptance scope, remaining risks, and any commercial remedies.
    • Schedule follow‑up checkpoint to validate remediation progress prior to final sign‑off.
    • Timeline Walkthrough
    • Create a prioritized list of lessons with clear owners and timelines.
    • Ensure RCA is documented for the top failures and linked to corrective actions.
    • Capture practices to standardize across future projects (standards, checklists, gating criteria).
    • Agree how lessons will be published and who receives them.
    • Produce a Lessons Learned report with RCA, recommended actions, and priority list.
    • Update project execution playbook and engineering checklists to incorporate approved changes.
    • Assign an owner to track implementation of each corrective action and report quarterly.
    • Share anonymized lessons with supplier network and SURF partners for cross‑project learning.
    • Reliability Results Summary
    • Confirm whether reliability outcomes meet contractual targets or require mitigation actions.
    • What Worked Well
    • Baseline: Success Signals Recap
    • Outcomes vs Success Signals (Condensed)
    • Triage Criteria & Prioritization Matrix
    • Update Reliability Model & Risk Profile
    • Financial & Schedule Impact
    • Shared Channel Design & Access
    • Measured Outcomes Presentation
    • What Broke & When
    • Monitoring & Diagnostics Plan
    • Gap Analysis & Quantification
    • Spares, Intervention & Contingency Planning
    • Root Cause Analysis (Top 3 Issues)
    • SLA, Escalation & Remedy Paths
    • Lessons, CAPAs & Commitments
First-Party AI

1-2 minutes please — Your AI agent is working

First-Party AI™ can make mistakes. Always check important information.